版權(quán)說明:本文檔由用戶提供并上傳,收益歸屬內(nèi)容提供方,若內(nèi)容存在侵權(quán),請(qǐng)進(jìn)行舉報(bào)或認(rèn)領(lǐng)
文檔簡(jiǎn)介
編審批頁
XX導(dǎo)流洞工程施工組織設(shè)計(jì)
合同編號(hào):GDC-200514
[實(shí)施階段]
批準(zhǔn):XX
審核:XX
校核:XX
編制:XX
建設(shè)單位:XX工程建設(shè)管理局(籌)
設(shè)計(jì)單位:XX集團(tuán)成都勘測(cè)設(shè)計(jì)研究院
監(jiān)理單位:XX二灘建設(shè)咨詢有限公司XX項(xiàng)目監(jiān)理部
施工單位:XX工程局XX施工局
年月
XX導(dǎo)流洞工程施工組織設(shè)計(jì)
[實(shí)施階段]
目錄
第一章綜合說明......................................................................1
1.1工程概況.........................................................................1
1.2主要施工項(xiàng)目及工程量............................................................2
1.2.1主要施工項(xiàng)目..................................................................2
1.2.2主要臨時(shí)工程項(xiàng)目..............................................................3
1.2.3主要工程量....................................................................3
1.3控制性進(jìn)度......................................................................4
1.3.1合同要求控制進(jìn)度形象..........................................................4
1.4水文氣象和工程地質(zhì)..............................................................4
1.4.1水文..........................................................................4
1.4.2氣象..........................................................................4
1.4.3工程地質(zhì)......................................................................5
1.5現(xiàn)場(chǎng)施工條件....................................................................6
1.5.1交通條件......................................................................6
1.5.2生產(chǎn)、生活營地................................................................6
1.5.3施工風(fēng)水電供應(yīng)................................................................6
1.5.4施工通信......................................................................7
1.5.5砂石骨料及混凝土供應(yīng)條件.....................................................7
1.6業(yè)主提供的材料和工程設(shè)備........................................................7
1.7渣場(chǎng)............................................................................7
1.8施工總體目標(biāo)....................................................................7
1.8.1工期目標(biāo)......................................................................7
1.8.2施工質(zhì)量目標(biāo)..................................................................8
183安全目標(biāo).......................................................................8
1.8.4環(huán)境保護(hù)、水土保持與文明施工目標(biāo).............................................8
第二章對(duì)工程施工的重點(diǎn)、難點(diǎn)的認(rèn)識(shí)及對(duì)策..........................................9
2.1施工重點(diǎn)、難點(diǎn)部位與項(xiàng)目........................................................9
2.1.1現(xiàn)場(chǎng)施工組織和管理是本工程順利實(shí)施的關(guān)鍵.....................................9
2.1.2進(jìn)出口圍堰布置位置、結(jié)構(gòu)形式以及后期拆除是本工程重點(diǎn)........................9
2.1.3施工區(qū)內(nèi)干線公路及其改線道路的保通本工程順利實(shí)施的前提......................9
2.1.4進(jìn)出口明挖及其支護(hù)施工是本標(biāo)工程的難點(diǎn)......................................9
2.1.5導(dǎo)流洞石方洞挖及混凝土襯砌是本標(biāo)的重點(diǎn)和難點(diǎn)...............................10
2.1.6導(dǎo)流洞石方洞挖及混凝土襯砌是本標(biāo)的重點(diǎn)和難點(diǎn)...............................10
2.2針對(duì)本工程項(xiàng)目重點(diǎn)、難點(diǎn)和關(guān)鍵線路應(yīng)采取的措施................................10
第三章施工總平面布置...............................................................12
3.1布置依據(jù)及原則.................................................................12
3.2總布置說明.....................................................................12
3.3施工交通.......................................................................13
3.3.1場(chǎng)外交通.....................................................................13
3.3.2場(chǎng)內(nèi)交通.....................................................................13
3.3.3施工支洞.....................................................................13
3.3.4進(jìn)、出口段改線...............................................................14
3.4施工供風(fēng).......................................................................15
3.4.1供風(fēng)量.......................................................................15
3.4.2供風(fēng)設(shè)備選型及布置...........................................................15
3.5施工供水.......................................................................16
3.5.1水源.........................................................................16
3.5.2用水量.......................................................................16
3.5.3取水及供水方式...............................................................17
3.5.4資源配置.....................................................................17
3.6施工供電.......................................................................18
3.6.1電源.........................................................................18
3.6.2用電負(fù)荷.....................................................................18
3.6.3用電規(guī)劃.....................................................................18
3.7照明與通訊.....................................................................20
3.7.1照明.........................................................................20
3.7.2通訊.........................................................................21
3.8砂石、混凝土系統(tǒng)...............................................................21
3.8.1砂石加工系統(tǒng).................................................................21
3.8.2混凝土拌和系統(tǒng)...............................................................22
3.9附助施工加工廠.................................................................22
3.9.1施工機(jī)械修配廠...............................................................22
3.9.2綜合加工廠..................................................................22
3.10倉庫和堆料場(chǎng)..................................................................23
3.10.1綜合倉庫....................................................................23
3.10.2堆料場(chǎng)......................................................................24
3.11辦公及生活營地.................................................................24
3.12試驗(yàn)室........................................................................25
3.13臨建工程量匯總及建筑面積、占地面積...........................................25
第四章施工總進(jìn)度計(jì)劃..............................................................28
4.1編制原則及依據(jù).................................................................28
4.1.1編制原則.....................................................................28
4.1.2編制依據(jù).....................................................................28
4.2控制性工期要求.................................................................28
4.3施工總程序安排和施工重點(diǎn).......................................................29
4.3.1第一階段.....................................................................29
4.3.2第二階段.....................................................................29
4.3.3第三階段.....................................................................29
4.4施工進(jìn)度計(jì)劃安排...............................................................30
4.4.1臨建工程施工進(jìn)度計(jì)劃安排.....................................................30
4.4.2導(dǎo)流洞進(jìn)出口圍堰施工進(jìn)度計(jì)劃安排............................................30
4.4.3土石方明挖及支護(hù).............................................................31
4.4.4石方洞挖及初期支護(hù)..........................................................31
4.4.5混凝土工程..................................................................31
4.4.6鉆孔和灌漿..................................................................32
4.5施工關(guān)鍵線路分析...............................................................32
4.6施工主要項(xiàng)目強(qiáng)度指標(biāo)分析.......................................................32
4.7施工進(jìn)度保證措施...............................................................33
4.7.1計(jì)劃保證措施.................................................................33
4.7.2技術(shù)保證措施................................................................34
第五章施工組織及資源配置..........................................................35
5.1施工組織管理...................................................................35
5.2現(xiàn)場(chǎng)組織機(jī)構(gòu)...................................................................35
5.2.1現(xiàn)場(chǎng)組織機(jī)構(gòu)設(shè)置原則.........................................................35
5.2.2現(xiàn)場(chǎng)組織機(jī)構(gòu).................................................................35
5.3職能部門職責(zé)...................................................................37
5.3.1施工局決策層.................................................................37
5.3.2施工局管理層.................................................................38
5.3.3施工局作業(yè)層.................................................................38
5.4組織機(jī)構(gòu)人員...................................................................39
5.5資源配置.......................................................................39
5.5.1擬投入本工程的主要施工設(shè)備..................................................39
5.5.2擬投入本工程的勞動(dòng)力計(jì)劃....................................................39
5.5.3主要材料用量計(jì)劃.............................................................39
第六章施工期水流控制..............................................................44
6.1概述............................................................................44
6.1.1工程項(xiàng)目范圍.................................................................44
6.1.2水流控制設(shè)計(jì)依據(jù)及原則......................................................44
6.1.3施工特點(diǎn)....................................................................44
6.2導(dǎo)流方式及標(biāo)準(zhǔn).................................................................44
6.2.1導(dǎo)流方式.....................................................................44
6.2.2導(dǎo)流標(biāo)準(zhǔn).....................................................................45
6.3圍堰設(shè)計(jì).......................................................................45
6.3.1圍堰平面布置.................................................................45
6.3.2圍堰結(jié)構(gòu)形式及工程量........................................................46
6.4圍堰施工.......................................................................46
6.4.1施工道路及風(fēng)、水、電.........................................................46
6.4.2土石子圍堰施工...............................................................47
6.4.3漿砌石圍堰..................................................................48
6.5施工期排水.....................................................................48
6.5.1漿砌石圍堰修筑期排水.........................................................48
6.5.2導(dǎo)流洞進(jìn)出口明渠基坑排水....................................................48
6.6安全渡汛措施...................................................................49
6.7施工進(jìn)度安排及施工強(qiáng)度.........................................................50
6.7.1施工進(jìn)度安排.................................................................50
6.7.2施工強(qiáng)度....................................................................50
6.8資源配置.......................................................................50
第七章土石方明挖、填筑及支護(hù)工程..................................................52
7.1工程概況.......................................................................52
7.1.1土石方明挖、填筑工程.........................................................52
7.1.2支護(hù)工程.....................................................................52
7.1.3進(jìn)出口開挖及支護(hù)工程施工特點(diǎn)................................................53
7.2土石方開挖施工方案.............................................................55
7.2.1施工布置.....................................................................55
7.2.2施工程序....................................................................57
7.3土石方開挖施工方法.............................................................58
7.3.1導(dǎo)流洞進(jìn)口土石方開挖.........................................................58
7.3.2導(dǎo)流洞出口土石方明挖........................................................61
7.4爆破控制.......................................................................61
7.4.1爆破器材選用.................................................................61
7.4.2主要技術(shù)措施................................................................61
7.4.3控制爆破參數(shù)................................................................61
7.4.4爆破試驗(yàn).....................................................................62
7.5支護(hù)施工.......................................................................64
7.5.1概述.........................................................................64
7.5.2施工方案.....................................................................64
7.5.3施工方法.....................................................................66
7.6施工強(qiáng)度及資源配置.............................................................74
7.6.1施工進(jìn)度計(jì)劃.................................................................74
7.6.2資源配置.....................................................................74
7.7雨季施工保證措施...............................................................74
第八章施工支洞的設(shè)計(jì)與施工........................................................78
8.1施工支洞設(shè)計(jì)...................................................................78
8.1.1施工支洞布置.................................................................78
8.1.2施工支洞洞臉設(shè)計(jì).............................................................78
8.1.3施工支洞斷面設(shè)計(jì).............................................................79
8.1.4洞內(nèi)支護(hù)設(shè)計(jì)................................................................79
8.1.5支洞封堵設(shè)計(jì)................................................................79
8.1.6堵頭灌漿設(shè)計(jì)................................................................80
8.2施工布置.......................................................................80
8.2.1施工道路.....................................................................80
8.2.2施工用風(fēng).....................................................................80
8.2.3施工用水.....................................................................80
8.2.4施工用電.....................................................................81
8.2.5施工排水.....................................................................81
8.2.6施工通風(fēng).....................................................................81
8.3施工程序及施工方案.............................................................81
8.3.1洞臉開挖及支護(hù)...............................................................81
8.3.2邊坡支護(hù)及安全防護(hù)...........................................................81
8.3.3石方洞挖.....................................................................82
8.3.4噴錨支護(hù).....................................................................84
8.4施工方法.......................................................................84
8.4.1鉆爆施工.....................................................................84
8.4.2錨桿施工.....................................................................87
8.4.3鋼筋掛網(wǎng)施工.................................................................87
8.4.4噴射混凝土施工...............................................................87
8.4.5鋼支撐支護(hù)...................................................................88
8.4.6施工期監(jiān)測(cè)..................................................................88
8.5資源配置.......................................................................89
8.5.1勞動(dòng)力組織...................................................................89
8.5.2機(jī)械設(shè)備配置.................................................................89
8.5.3主要材料計(jì)劃.................................................................89
第九章石方洞挖及支護(hù)工程...........................................................92
9.1工程概述.......................................................................92
9.2洞挖施工特點(diǎn)...................................................................92
9.3施工布置.......................................................................93
9.3.1施工通道.....................................................................93
9.3.2風(fēng)、水、電布置...............................................................93
9.3.3洞挖通風(fēng).....................................................................94
9.3.4洞內(nèi)施工用風(fēng)、水、電布置原則................................................95
9.4施工作業(yè)區(qū)劃分.................................................................95
9.5進(jìn)出口段開挖程序...............................................................95
9.5.1開挖施工原則.................................................................96
9.5.2洞挖工藝流程及方法...........................................................96
9.5.3進(jìn)出口段開挖施工措施........................................................98
9.6洞身主體段開挖程序.............................................................99
9.7洞挖作業(yè)循環(huán)時(shí)間..............................................................101
9.7.1上部開挖....................................................................101
9.7.2中部上層開挖................................................................101
9.7.3中部下層開挖................................................................102
9.7.4底板開挖....................................................................102
9.8支護(hù)施工工藝..................................................................103
9.8.1錨桿........................................................................103
9.8.2噴射碎施工..................................................................103
9.8.3鋼支撐、格柵拱..............................................................104
9.9塌方的預(yù)防及地下水處理........................................................105
9.9.1塌方的預(yù)防與處理............................................................105
9.9.2對(duì)地下水的處理..............................................................106
9.10施工期監(jiān)測(cè)...................................................................106
9.10.1地質(zhì)和初期支護(hù)狀態(tài)觀測(cè).....................................................106
9.10.2地質(zhì)超前預(yù)報(bào)...............................................................106
9.10.3周邊位移量測(cè)...............................................................107
9.10.4頂拱下沉量測(cè)...............................................................107
9.11資源配置.......................................................................107
第十章鉆孔與灌漿工程...............................................................110
10.1概況..........................................................................110
10.1.1工程項(xiàng)目及工程量...........................................................110
10.1.2地質(zhì)條件...................................................................110
10.1.3施工特點(diǎn)...................................................................111
10.2施工臨建布置.................................................................111
10.2.1制漿站.....................................................................111
10.2.2施工供水、供電、供風(fēng)及通訊................................................111
10.2.3施工排水、排污布置.........................................................112
10.2.4灌漿材料及施工設(shè)備運(yùn)輸.....................................................112
10.2.5鉆灌平臺(tái)車布置.............................................................112
10.3施工方法和措施...............................................................112
10.3.1施工程序...................................................................112
10.3.2邊坡固結(jié)灌漿...............................................................112
10.3.3回填灌漿...................................................................112
10.3.4固結(jié)灌漿...................................................................113
10.3.5洞外帷幕灌漿施工...........................................................115
10.3.6排水孔施工.................................................................118
10.4施工進(jìn)度計(jì)劃.................................................................118
10.5資源配置......................................................................119
第十一章混凝土工程................................................................120
11.1概述..........................................................................120
11.1.1工程特性及工程量...........................................................120
11.1.2校施工特點(diǎn).................................................................120
11.2施工布置......................................................................120
11.2.1混凝土施工道路.............................................................120
11.2.2風(fēng)、水、電.................................................................121
11.2.3混凝土供應(yīng).................................................................121
11.2.4施工機(jī)械布置...............................................................121
11.3施工強(qiáng)度分析及資源配置.......................................................121
11.3.1主要機(jī)械施工能力計(jì)算.......................................................121
11.3.2施工強(qiáng)度分析...............................................................122
11.3.3資源配置...................................................................123
11.4混凝土施工....................................................................124
11.4.1洞內(nèi)砂施工方案.............................................................124
11.4.2洞外碎施工方案.............................................................126
11.4.3施工方法...................................................................127
11.4.4磴運(yùn)輸、入倉、澆筑.........................................................130
11.4.5磅的保護(hù)、養(yǎng)護(hù)............................................................130
11.4.6碎的溫度控制..............................................................131
11.5模板工程......................................................................131
11.5.1洞內(nèi)模板工程...............................................................131
11.5.2洞外模板工程...............................................................132
11.6鋼筋工程......................................................................132
11.6.1洞內(nèi)鋼筋制作和安裝.........................................................132
11.6.2進(jìn)出口及閘室的鋼筋制安....................................................134
11.7施工進(jìn)度計(jì)劃..................................................................135
11.7.1導(dǎo)流洞進(jìn)口引渠及閘室碎施工進(jìn)度計(jì)劃........................................135
11.7.2隧洞碎施工進(jìn)度計(jì)劃.........................................................135
第十二章砌體及鋼筋籠填石工程.....................................................136
12.1概述..........................................................................136
12.2施工布置.....................................................................136
12.2.1材料堆放場(chǎng).................................................................136
12.2.2砂漿站.....................................................................136
12.2.3鋼筋籠加工.................................................................136
12.2.4材料運(yùn)輸...................................................................136
12.3施工進(jìn)度計(jì)劃.................................................................136
12.4砌石體工程...................................................................136
12.4.1材料選擇...................................................................136
12.4.2漿砌石砌筑施工.............................................................137
12.4.3水泥砂漿勾縫防滲...........................................................138
12.4.4砌體質(zhì)量控制及檢查驗(yàn)收....................................................138
12.4.5砌體工程質(zhì)量保證措施.......................................................139
12.5鋼筋籠填石施工...............................................................140
12.5.1施工準(zhǔn)備...................................................................140
12.5.2石料運(yùn)輸...................................................................140
12.5.3填筑前的準(zhǔn)備工作...........................................................140
12.5.4鋼筋石籠填筑...............................................................140
12.5.5鋼筋籠石填筑質(zhì)量安全保證措施..............................................141
12.6資源配置.....................................................................141
第十三章門槽及填框安裝.............................................................142
13.1門槽及填框安裝概述............................................................142
13.1.1安裝工作范圍...............................................................142
13.1.2安裝工作主要內(nèi)容...........................................................142
13.1.3安裝工程量.................................................................142
13.2門槽及門槽填框安裝............................................................142
13.2.1門槽及門槽填框安裝程序.....................................................142
13.2.2門槽及門槽填框運(yùn)輸和吊裝...................................................143
13.2.3安裝前的準(zhǔn)備工作...........................................................144
13.2.4安裝工藝...................
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。
最新文檔
- 2024年寧南縣三上數(shù)學(xué)期末聯(lián)考模擬試題含解析
- 2024年遼寧省本溪滿族自治縣數(shù)學(xué)三上期末學(xué)業(yè)水平測(cè)試模擬試題含解析
- 2024年江蘇省蘇州楓華學(xué)校三年級(jí)數(shù)學(xué)第一學(xué)期期末達(dá)標(biāo)檢測(cè)試題含解析
- 七年級(jí)人教版思想品德上冊(cè)單元復(fù)習(xí)提要課件
- 2025年護(hù)士執(zhí)業(yè)空間操作試題及答案
- 藥學(xué)研究生課程試題及答案
- 關(guān)鍵知識(shí)點(diǎn)主管護(hù)師試題及答案
- 2025年執(zhí)業(yè)藥師考試高頻考點(diǎn)試題及答案
- 2025年執(zhí)業(yè)藥師考試臨床技術(shù)試題及答案
- 2025年醫(yī)師考試重視臨床應(yīng)用能力的原因與方法研究試題及答案
- 2025年湖南湘投控股集團(tuán)有限公司招聘筆試參考題庫含答案解析
- 綠色建筑材料在土木工程施工中的應(yīng)用研究
- 第二十九節(jié) 商業(yè)模式創(chuàng)新及案例分析
- 中國鐵路沈陽局集團(tuán)有限公司招聘筆試沖刺題2025
- 2024年度醫(yī)療設(shè)備報(bào)廢回收與資源化利用合同3篇
- 醫(yī)療器械的維護(hù)和保養(yǎng)方法
- 石材養(yǎng)護(hù)報(bào)價(jià)單
- 世界各地的建筑·小學(xué)生課件
- 試題-醫(yī)療器械質(zhì)量管理培訓(xùn)
- 海外醫(yī)療合同模板
- 微笑曲線中文版課件
評(píng)論
0/150
提交評(píng)論