施工組織設(shè)計目錄
第一章施工規(guī)劃總說明....................................................0
1.1說明..............................................................0
1.1.1工程概況.....................................................0
1.1.2水文氣象.....................................................0
1.1.3工程地質(zhì)......................................................1
1.1.4對外交通.....................................................2
1.2合同項目和工作范圍................................................2
第二章施工總體布置......................................................3
2.1施工總布置的條件及原則.............................................3
2.1.1施工總布置條件................................................3
2.1.2施工總布置原則................................................3
2.1.3施工總布置內(nèi)容................................................3
2.1.4引用標(biāo)準(zhǔn)......................................................4
2.2施工交通...........................................................4
2.2.1對外交通......................................................4
2.2.2內(nèi)部交通......................................................4
2.3風(fēng)、水、電、照明、通訊系統(tǒng)及郵政服務(wù)...............................4
2.3.1施工供電.....................................................4
2.3.2施工供水.....................................................8
2.3.3施工供風(fēng).....................................................9
2.3.4施工照明.....................................................9
2.3.5施工通信...................................................10
2.3.6郵政服務(wù)....................................................11
2.4砂石料場開采加工系統(tǒng)..............................................11
2.5混凝土生產(chǎn)系統(tǒng)....................................................11
2.6臨時工廠設(shè)施......................................................11
2.6.1機械修配廠...................................................11
2.6.2鋼筋加工廠..................................................11
2.6.3木材加工廠..................................................13
2.6.4預(yù)制混凝土構(gòu)件加工廠.........................................13
2.7倉庫和堆、存料場..................................................13
2.7.1水泥倉庫.....................................................13
2.7.2鋼材倉庫.....................................................13
2.7.3炸藥庫......................................................13
2.8棄渣場............................................................14
2.9臨時生產(chǎn)管理和生活設(shè)施............................................14
2.10工地試驗室的布置.................................................14
2.11施工用地計劃.....................................................14
第三章施工導(dǎo)流工程.....................................................16
3.1概述..............................................................16
3.2引用標(biāo)準(zhǔn)和規(guī)范規(guī)程................................................16
3.3施工圍堰設(shè)計......................................................16
3.4圍堰填筑施工......................................................17
3.5圍堰拆除..........................................................17
3.6施工排水..........................................................17
3.6.1基坑初期排水................................................17
3.6.2基坑經(jīng)常性排水..............................................17
3.6.3基坑排水設(shè)備................................................17
3.7截流..............................................................17
3.8臨時斷航..........................................................18
3.9下閘封堵和水庫蓄水................................................18
3.10安全度汛和排冰凌.................................................18
第四章施工總進度計劃...................................................19
4.1施工總進度計劃編制依據(jù)............................................19
4.2施工總進度計劃編制原則............................................19
4.3控制性工期要求....................................................20
4.4有效工作日分析....................................................20
4.5主要工程項目施工進度安排..........................................20
4.6關(guān)鍵線路..........................................................22
4.6.1關(guān)鍵線路....................................................22
4.6.2關(guān)鍵線路上的控制工期........................................23
4.6.3施工總進度橫道圖及網(wǎng)絡(luò)圖....................................23
4.7工期保證措施......................................................23
4.7.1組織保證措施................................................24
4.7.2加強計劃管理................................................24
4.7.3技術(shù)保證措施................................................24
4.7.4設(shè)備、材料保證措施..........................................25
4.7.5加強對外聯(lián)系與協(xié)作..........................................25
第五章土建工程施工方案................................................26
5.1土石方開挖........................................................26
5.1.1概述.........................................................26
5.1.2施工布置....................................................27
5.1.3場地清理....................................................28
5.1.4施工工藝.....................................................28
5.1.5安全防護....................................................30
5.1.6開挖質(zhì)量控制措施............................................31
5.1.7主要施工設(shè)備................................................31
5.2支護工程..........................................................32
5.2.1概述........................................................32
5.2.2引用標(biāo)準(zhǔn)和規(guī)程規(guī)范..........................................32
5.2.3巖石錨桿....................................................33
5.2.4噴射混凝土.................................................35
5.2.5臨時支護....................................................38
5.2.6主要施工設(shè)備................................................38
5.3土石方填筑工程...................................................39
5.3.1概述.........................................................39
5.3.2填筑施工....................................................39
5.3.3填筑施工質(zhì)量檢查和驗收......................................40
5.3.4主要機械設(shè)備配備............................................41
5.4混凝土工程.......................................................41
5.4.1概述.........................................................41
5.4.2模板工程.....................................................42
5.4.3鋼筋.........................................................44
5.4.4混凝土原材料...............................................46
5.4.5混凝土拌和及運輸.............................................48
5.4.6混凝土澆筑...................................................49
5.4.7預(yù)制混凝土.................................................51
5.4.8混凝土表面的修整.............................................53
5.4.9混凝土養(yǎng)護和表面保護.........................................54
5.4.10混凝土溫控措施..............................................55
5.4.11止水、伸縮縫和埋設(shè)件........................................56
5.4.12質(zhì)量檢查和驗收..............................................57
5.4.13混凝土施工質(zhì)量控制..........................................59
5.4.14機械設(shè)備和人力資源配置......................................60
5.5鉆孔與灌漿........................................................61
5.5.1施工內(nèi)容.....................................................61
5.5.2施工布置.....................................................62
5.5.3灌漿材料.....................................................62
5.5.4主要施工設(shè)備...............................................64
5.5.5鉆孔作業(yè)...................................................65
5.5.6鉆孔沖洗和壓水試驗...........................................65
5.5.7灌漿試驗.....................................................66
5.5.8制漿.........................................................67
5.5.9帷幕灌漿.....................................................68
5.5.10質(zhì)量保證措施...............................................70
5.6砌體工程..........................................................72
第六章金屬結(jié)構(gòu)制作與安裝..............................................78
6.1概述..............................................................78
6.1.1制作安裝項目...............................................78
6.1.2引用標(biāo)準(zhǔn)和規(guī)范..............................................78
6.2施工進度計劃......................................................81
6.2.1控制性工期..................................................81
6.2.2施工進度計劃................................................81
6.3金屬結(jié)構(gòu)制作.....................................................81
6.3.1主要工作內(nèi)容................................................81
6.3.2設(shè)備制造前的準(zhǔn)備............................................82
6.3.3尾水事故門門槽埋件制造......................................84
6.3.4檢修門、攔污柵埋件制造......................................85
6.3.5尾水事故閘門及平面檢修閘門制造..............................86
6.3.6攔污柵制造..................................................92
6.3.7啟閉設(shè)備制造................................................94
6.4金屬結(jié)構(gòu)安裝.....................................................95
6.4.1主要工作內(nèi)容................................................95
6.4.2埋件安裝...................................................95
6.4.3閘門安裝.....................................................96
6.4.4固定卷揚啟閉機安裝...........................................97
6.4.5雙向門機安裝.................................................97
6.5技術(shù)供應(yīng)..........................................................101
第七章機電設(shè)備安裝...................................................103
7.1工程概述.........................................................103
7.1.1概述........................................................103
7.1.2工程量清單..................................................103
7.2施工布置..........................................................121
7.2.1施工人員組織................................................121
7.2.2施工臨建設(shè)施................................................121
7.2.3設(shè)備倉儲倒運................................................123
7.2.4工程協(xié)調(diào)...................................................124
7.2.5工期計劃...................................................124
7.2.6勞動力計劃..................................................125
7.3水輪發(fā)電機組及其輔助設(shè)備安裝.....................................125
7.3.1工程內(nèi)容....................................................125
7.3.3安裝前準(zhǔn)備工作..............................................126
7.3.4水輪發(fā)電機組安裝程序........................................127
7.3.5水輪機安裝過程及技術(shù)措施....................................128
7.3.6發(fā)電機安裝過程及技術(shù)措施....................................143
7.3.7質(zhì)量保證措施................................................153
7.3.8安全文明施工與環(huán)境保護......................................154
7.4水力機械輔助及其他設(shè)備安裝........................................155
7.4.1概述........................................................155
7.4.2施工前準(zhǔn)備及主要技術(shù)要求....................................155
7.4.3施工布置....................................................156
7.4.4施工進度安排..............................................156
7.4.5水力機械輔助設(shè)備安裝流程....................................156
7.4.6施工技術(shù)措施..............................................157
7.4.7主要施工機械設(shè)備投入........................................160
7.4.8勞動力組合................................................160
7.4.9工程檢查和驗收............................................160
7.4.10依據(jù)規(guī)范、標(biāo)準(zhǔn).............................................160
7.5廠內(nèi)橋式起重機安裝.............................................161
7.6電站電氣設(shè)備安裝................................................163
7.6.1電工一次設(shè)備與裝置安裝.....................................163
7.6.2電工二次盤柜、電纜安裝及接線...............................176
7.6.3全廠通信系統(tǒng)...............................................177
7.6.4電氣試驗..................................................178
7.6.5系統(tǒng)調(diào)試..................................................182
7.6.6機組啟動試運行方案.........................................183
第八章施工組織管理.....................................................188
8.1施工組織管理基本原則.............................................188
8.2項目管理機構(gòu).....................................................188
8.2.1項目管理機構(gòu)................................................188
8.2.2項目管理機構(gòu)說明...........................................188
8.2.3施工區(qū)域管理...............................................190
第九章工程質(zhì)量管理...................................................191
9.1概述.............................................................191
9.2質(zhì)量保證體系.....................................................191
9.2.1質(zhì)量方針和質(zhì)量目標(biāo)..........................................191
9.2.2質(zhì)量保證體系...............................................192
9.2.3質(zhì)量管理機構(gòu)及職責(zé)..........................................192
9.2.4質(zhì)量保證體系主要控制要素....................................195
9.3質(zhì)量保證措施.....................................................197
9.4獎罰措施.........................................................198
9.4.1獎勵基金與獎勵..............................................198
9.4.2施工質(zhì)量優(yōu)秀班組和先進個人的評選條件........................198
9.4.3質(zhì)量問題處罰................................................199
第十章安全施工........................................................200
10.1安全生產(chǎn)方針及目標(biāo)..............................................200
10.2安全生產(chǎn)組織機構(gòu)................................................200
10.3安全生產(chǎn)控制體系................................................200
10.4各部門安全生產(chǎn)崗位職責(zé)..........................................200
10.5安全技術(shù)措施....................................................203
10.6衛(wèi)生、防疫、防病、事故預(yù)防措施..................................209
第H^一章文明施工......................................................210
11.1文明施工的目標(biāo)..................................................210
11.2文明施工組織機構(gòu)建立...........................................210
11.3文明施工措施...................................................210
11.4文明施工考核辦法...............................................212
11.5文明施工管理辦法...............................................212
第十二章環(huán)境保護與水土保持...........................................213
12.1環(huán)境保護........................................................213
12.1.1引用的法律法規(guī)............................................213
12.1.2引用標(biāo)準(zhǔn)...................................................213
12.1.3環(huán)境保護方針..............................................214
12.1.4環(huán)境保護目標(biāo)...............................................214
12.1.5生態(tài)環(huán)境保護...............................................216
12.2水土保持.......................................................216
12.2.1執(zhí)行水土保持措施計劃......................................216
12.2.2做好水土保持工程措施.....................................217
12.3環(huán)境清理.......................................................217
12.3.1環(huán)境清理措施計劃..........................................217
12.3.2環(huán)境清理..................................................217
第十三章資源配置.....................................................218
13.1勞動力組織計劃.................................................218
13.2主要材料供應(yīng)計劃................................................219
13.3主要施工設(shè)備配備................................................220
第一章施工規(guī)劃總說明
1.1說明
1.1.1工程概況
東方紅電站水庫是以灌溉、發(fā)電為主,兼顧養(yǎng)殖旅游等綜合利用的水利工程。水
庫規(guī)劃2010年灌溉水面積1.03萬畝,灌溉引用流量1.03X104m3/s,電站總裝機2750
kW,年發(fā)電量約700X10」kW?h。建庫四十多年來,對發(fā)展農(nóng)業(yè)生產(chǎn)、支援地方經(jīng)濟建
設(shè)發(fā)揮了很大作用。
水庫總庫容(校核水位下)為3025X104一,校核洪水位為234.22m,設(shè)計洪水位
為232.35m,正常蓄水位為225.50m。
根據(jù)《水利水電工程等級劃分及洪水標(biāo)準(zhǔn)》(SL252-2000),依據(jù)總庫容確定東方
紅水電站工程規(guī)模屬中型,工程等別為IH等工程。本工程最大壩高10m,正常蓄水位
相應(yīng)庫容204xl04m3,水庫下游為回龍山水庫,所以,擋水壩失事后不會造成大的損
失,根據(jù)規(guī)范222條規(guī)定,建筑物級別可以降低一級,故確定主要建筑物級別為4級,
次要建筑物級別為5級。
洪水標(biāo)準(zhǔn)按山區(qū)、丘陵區(qū)標(biāo)準(zhǔn)確定,根據(jù)規(guī)范3.2.2條規(guī)定,主要建筑物洪水標(biāo)
準(zhǔn):設(shè)計洪水重現(xiàn)期為30年,校核洪水重現(xiàn)期為200年。
東方紅水電站由溢流壩、左岸河床式發(fā)電廠房及變電站,右岸引水渠等建筑物組
成。
溢流壩段由寬頂堰和實用堰兩種堰型組成,溢流壩段總長253m。
左岸廠房內(nèi)裝兩臺GZ(K231)-WP-335型貫流式水輪發(fā)電機組,單機容量3000k肌
總裝機6000kW,廠房總長50.5m,寬為13.9m,其中主機間長30m,安裝間長20.5m,
最大高度37.35m,主機間與安裝間之間設(shè)有永久結(jié)構(gòu)縫。
副廠房分別布置在安裝間下層和尾水平臺下層,安裝間下部副廠房分兩層,尾水
副廠房分兩層,各層之間設(shè)有樓梯作為上下聯(lián)系通道。
變電站布置在尾水平臺上。
1.1.2水文氣象
(1)氣象資料
東方紅電站水庫氣象資料見表l-lo
表IT東方紅電站水庫氣象資料
序號名稱單位溫度備注
1多年平均氣溫℃6.3
2最高氣溫℃42.0
3最低氣溫℃-35.7
(2)風(fēng)速、吹程
東方紅電站水庫受地理位置,周邊地形的影響,多年平均每年度6月至9月屬于
大風(fēng)多發(fā)月,多年平均最大風(fēng)速未17.7m/s,吹程:D=lkwo
1.1.3工程地質(zhì)
渾江在東方紅由東北流向南西,河谷寬闊,呈不對稱“U"型。右岸階地不發(fā)育,
局部發(fā)育漫灘。山體底高程為223?225m,比高80?100m,山體下部坡比為23°?45°,
局部陡壁出露,左岸一、二級階地和漫灘發(fā)育,地形寬闊,一級階地前、后緣高程分
別為225?235m。
渾江主流在左側(cè),河床寬60m,右側(cè)有小支流,兩者之間形成卵礫石漫灘,高程
221m左右,江底高程219nl左右,局部為218m。
壩址、廠房區(qū)地層巖性為上侏羅系黎樹溝組的火山巖系,巖性為安山凝灰?guī)r、灰
綠色、紫灰色,凝灰結(jié)構(gòu),層狀構(gòu)造。巖石成分為晶屑、巖屑、火山灰,凝灰質(zhì)膠結(jié)。
巖質(zhì)較堅硬,抗風(fēng)化能力較強,無全風(fēng)化巖,強風(fēng)化巖厚度50cm左右。
第四系沖積層為卵礫石層,左岸一級階地鉆孔揭露,其厚度為7.4?7.5m;河床
1.5?4.0m。卵礫石含量80%,透水性強。
巖層產(chǎn)狀:走向N20°~40°E,傾NW,傾角20°?35°。主要節(jié)理有下列三組:
⑴走向N25°~35°E,傾向SE,傾角80°-85°。⑵走向N35°~50°W,傾向NE,
傾角80°~85°o⑶走向N10°~15°W,傾向SW,傾角75°~80°。
地下水按埋藏深度類型分為孔隙潛水和基巖裂隙水,孔隙潛水在左岸一級階地,
埋深一般為3?4m,透水性強。河床上部巖體透水率為3.5~9.5Lu,為弱透水巖體。
河水為重碳酸鈣型水,PH值為6.4左右,對混凝土具有一般酸性弱腐蝕性侵蝕。
1.1.4對外交通
(1)對外交通條件
本工程距桓仁縣城較近,現(xiàn)有縣級道路、鄉(xiāng)級道路交通十分便利,各級公路網(wǎng)四
通八達,所以該工程對外交通主要采用公路運輸方式。工程所需的鋼材.、水泥及生活
物資等,可在桓仁縣購買。
(2)場內(nèi)交通
場內(nèi)交通運輸主要是土石方、混凝土、水泥、鋼材等物資的運輸。場內(nèi)交通采用
公路運輸方式。工程區(qū)域現(xiàn)有道路規(guī)劃有序,且路況較好,基本滿足施工交通需要。
1.2合同項目和工作范圍
除本合同另有規(guī)定外,本合同包括承建的永久工程和臨時工程的施工和竣工驗收
前的維護,其中包括為完成本合同工程所需的材料、勞務(wù)、施工設(shè)備和其它必要的手
段與臨時設(shè)施。這些工程應(yīng)嚴格按合同或監(jiān)理人的批準(zhǔn)執(zhí)行。
本工程項目的主要工作內(nèi)容包括:
(1)土建工程:主要包括土方開挖和回填、混凝土工程、砌體工程、帷幕灌漿。
(2)金屬結(jié)構(gòu)制作及安裝:主要包括進水口、尾水的各式閘門、攔污柵、埋件及
啟閉機等。
(3)機電設(shè)備安裝:
水輪機、調(diào)速系統(tǒng)、水輪發(fā)電機、技術(shù)供水系統(tǒng)、機組檢修、廠房滲漏排水系統(tǒng)、
透平油系統(tǒng)、壓縮空氣系統(tǒng)、水力監(jiān)測系統(tǒng)、消防系統(tǒng)、采暖通風(fēng)系統(tǒng)、給水排水系
統(tǒng)、橋機、發(fā)電機電壓配電裝置工程、變電站系統(tǒng)工程、廠用電供電系統(tǒng)工程、照明
系統(tǒng)、全廠動力電纜及電纜管架、電纜防火系統(tǒng)工程、接地系統(tǒng)工程、電氣調(diào)整、全
廠通信系統(tǒng)、全廠控制保護及測量設(shè)備工程、全廠直流系統(tǒng)設(shè)備工程、全廠控制電纜、
電線工程。
(4)其他相關(guān)的臨時工程。
第二章施工總體布置
2.1施工總布置的條件及原則
2.1.1施工總布置條件
(1)現(xiàn)場自然條件;
(2)場內(nèi)外交通條件;
(3)發(fā)包人規(guī)劃的施工臨時用地條件;
(4)主要材料供應(yīng)方式。
2.1.2施工總布置原則
根據(jù)現(xiàn)有的場地條件,結(jié)合場內(nèi)外交通路線,按照工程施工的需要,進行施工生
產(chǎn)、生活區(qū)的規(guī)劃與管理。
(1)充分考慮到招標(biāo)文件關(guān)于本工程施工進度、施工質(zhì)量、安全、環(huán)保和文明施
工方面的要求,所有臨建設(shè)施及施工道路均按招標(biāo)文件要求,布置在本合同允許范圍
內(nèi)。
(2)施工區(qū)規(guī)劃做到布置整齊合理、外表美觀。臨建設(shè)施規(guī)模根據(jù)施工進度安排
進行規(guī)劃和設(shè)計,做到簡單實用、布置緊湊、合理;施工布置做到能充分發(fā)揮設(shè)施的
生產(chǎn)能力,滿足施工總進度和施工強度的要求。
(3)節(jié)約用地,本著利于生產(chǎn)、方便生活、易于管理的原則布置,根據(jù)招標(biāo)標(biāo)段
劃分,結(jié)合現(xiàn)場地形條件,施工設(shè)施等采用集中布置方式。并嚴格執(zhí)行有關(guān)消防、衛(wèi)
生和環(huán)境保護的相關(guān)規(guī)定。
(4)施工營地內(nèi)各場區(qū)分開布置,相對獨立,盡可能減少彼此作業(yè)時的相互干擾。
(5)施工營地設(shè)置有效的防護和排水系統(tǒng),滿足場地的防護和排水要求。施工布
置注意環(huán)境保護,避免損害公眾利益,并考慮為發(fā)包人、監(jiān)理人提供方便。施工過程
中,加強文物保護和水土保持,不人為破壞施工區(qū)內(nèi)外的保護設(shè)施。
2.1.3施工總布置內(nèi)容
本工程施工總布置的內(nèi)容包括:現(xiàn)場施工測量、現(xiàn)場試驗、施工交通、施工供電、
施工供水、施工供風(fēng)、施工照明、施工通信、郵政服務(wù)、砂石料料物開采加工系統(tǒng)、
混凝土生產(chǎn)系統(tǒng)、機械修配廠、加工廠、倉庫、存料場、棄料場以及施工現(xiàn)場辦公和
生活建筑設(shè)施等。
2.1.4引用標(biāo)準(zhǔn)
(1)《生活飲用水衛(wèi)生標(biāo)準(zhǔn)》(GB5749-2006);
(2)《水工建筑物地下開挖工程施工規(guī)范》(SL378-2007);
(3)《水利水電工程施工組織設(shè)計規(guī)范》(SL303-2004);
(4)《水利水電工程施工測量規(guī)范》(SL52-1993)o
2.2施工交通
2.2.1對外交通
本工程距桓仁縣城較近,現(xiàn)有縣級道路、鄉(xiāng)級道路交通十分便利,各級公路網(wǎng)四
通八達,所以該工程對外交通主要采用公路運輸方式。工程所需的鋼材、水泥及生活
物資等,可在桓仁縣購買。
2.2.2內(nèi)部交通
根據(jù)招標(biāo)文件規(guī)定及現(xiàn)場施工條件,修建本合同施工區(qū)內(nèi)自發(fā)包人提供的道路至
各施工點的全部施工道路、橋涵、交通隧道和停車場,并在合同實施期間負責(zé)管理和
維護(包括管理和維護發(fā)包人提供的施工道路)。
2.3風(fēng)、水、電、照明、通訊系統(tǒng)及郵政服務(wù)
2.3.1施工供電
(1)設(shè)計標(biāo)準(zhǔn)
遵循《供配電系統(tǒng)設(shè)計規(guī)范》(GB5002—95),參照《水利水電施工組織設(shè)計手冊》
等相關(guān)規(guī)程、規(guī)范資料,并結(jié)合招標(biāo)文件(技術(shù)條款)進行設(shè)計。
(2)10KV供電線路
根據(jù)招標(biāo)文件業(yè)主提供電源終端桿位置和施工組織設(shè)計中各供電區(qū)施工變壓器計
劃安裝位置。本標(biāo)段需要架設(shè)的10KV線路共一處。
1)倉庫、生活供電區(qū):業(yè)主供電接引點至加工廠架設(shè)條10KV線路,線路長度
約500m,導(dǎo)線規(guī)格為LGJ-35mm2鋼芯鋁絞線。
2)開關(guān)站:業(yè)主供電接引點至加工廠架設(shè)一條10KV線路,線路長度約200m,導(dǎo)
線規(guī)格為LGJ-35mm2鋼芯鋁絞線
(3)各施工部位用電負荷及供電方案
1)用電負荷
本部位施工用電,前期主要用電負荷有初期基坑排水水泵用電、施工照明、施工
供水水泵等,后期主要用電負荷有經(jīng)常性基坑排水、施工作業(yè)面照明、混凝土澆筑施
工用電,混凝土拌和站用電等。
2)低壓線路布置
基坑排水用電:從變壓器敷設(shè)兩條yc-3*95+l*50橡膠絕緣電纜至基坑排水泵。
(4)施工輔助生產(chǎn)企業(yè)及生活營區(qū)供電區(qū)
1)用電負荷統(tǒng)計
本部位分施工輔助生產(chǎn)企業(yè)、倉庫區(qū)和生活營區(qū)用電,主要用電負荷統(tǒng)計
見表2T所示。
表2T各附屬生產(chǎn)企業(yè)、生活營地用電負荷統(tǒng)計表
序號設(shè)備名稱設(shè)備總功率(KW)需要系數(shù)計算負荷(KW)
1機械修配廠1660.466.4
2鋼筋加工廠2080.362.4
3木材加工廠560.633
4綜合倉庫2020
5生活區(qū)325(高峰)0.9292.5
6供水泵7.5*20.57.5
7料場250.615
8其它2525
合計521.8
2)供電變壓器的選擇
根據(jù)本供電區(qū)用電負荷統(tǒng)計,高峰期計算負荷476Kw,選擇變壓器型號為
S9-600-10/0.4,容量為600KVA,安裝在施工輔助生產(chǎn)企業(yè)區(qū)。
3)低壓線路布置
生活區(qū)用電:從變壓器架設(shè)一條BLV-3*150+l*70塑料絕緣架空線路(同桿雙層)
至生活區(qū),倉庫用電從生活區(qū)供電線路接引;
施工工廠作業(yè)區(qū)用電:從變壓器架設(shè)一條LJ-3*120+l*50鋼芯鋁絞線至各施工作
業(yè)場地。
(5)無功率補償裝置
為了提高施工用電效率,減少電網(wǎng)無功損耗,在每臺變壓器低壓側(cè),并聯(lián)配置一
面BJ(F)—3Z系列自動無功率補償柜,具體規(guī)格按照變壓器容量選擇配套電容器柜,
可將功率因數(shù)提高到0.9以上,滿足當(dāng)?shù)毓╇姽芾聿块T對功率因數(shù)的要求。
(6)備用電源
為了保證重要負荷不間斷供電,保證重點部位在停電和事故情況下正常施工,備
用160KW柴油發(fā)電機2臺,做備用電源用,此發(fā)電機為無基礎(chǔ)可移動式,可根據(jù)施工
需要運到工作地點,使用方便、靈活。
(7)施工用電安全措施
為了保證施工生產(chǎn)正常進行,保證施工人員及設(shè)備安全,施工中應(yīng)做到如下用電
要求:
1)凡是與電有可能接觸人員,在施工前應(yīng)進行一次安全用電知識學(xué)習(xí),使每個
職工都懂得安全用電知識,并應(yīng)掌握觸電急救的方法。
2)電氣設(shè)備的采購、使用、管理應(yīng)嚴格執(zhí)行國家或部委有關(guān)設(shè)備管理與使用的
技術(shù)標(biāo)準(zhǔn),并根據(jù)設(shè)備使用手冊制定具體的使用管理制度。
3)對于一些經(jīng)常移動的設(shè)備,要有臨時接地措施,并在電源側(cè)有漏電保護裝置。
4)設(shè)備的外殼應(yīng)可靠接地,接地電阻應(yīng)符合有關(guān)規(guī)程規(guī)定的數(shù)值,易受雷擊,
可燃,易爆場所應(yīng)設(shè)置防雷保護裝置。
5)經(jīng)常檢查用電設(shè)備及臨時線路電纜的絕緣情況,責(zé)任落實到人,檢查結(jié)果應(yīng)
有書面記錄,重要地點應(yīng)有專人負責(zé),發(fā)現(xiàn)問題要及時處理。
6)電氣工作人員要持證上崗,禁止無證操作。
7)電氣工作操作時,要嚴格執(zhí)行“兩票”“三制”制度,杜絕一切違章操作。
8)電工作業(yè)及經(jīng)常接觸帶電設(shè)備人員,應(yīng)配齊輔助絕緣工具,防止發(fā)生觸電事
故。
9)在不便于使用常規(guī)照明設(shè)備的工作面,應(yīng)采用特殊的照明措施。
10)設(shè)備安裝時要制定安全技術(shù)措施,保證設(shè)備與人身安全。
11)開關(guān)應(yīng)按照設(shè)備額定容量配備,電流較大的電器啟動時應(yīng)按規(guī)程使用磁力啟
動器或交流接觸器,危險場所及人員易觸及到的場所必須配備漏電保護裝置。
12)在作業(yè)區(qū)內(nèi),對一些有可能觸電的區(qū)域,供電設(shè)施必須設(shè)置明顯的警示標(biāo)志,
并應(yīng)有防護措施。
13)工地臨時用電,檢修電氣設(shè)備,應(yīng)找電工完成,不得私自操作。
14)定期召開安全用電會議,找問題、查隱患、制定預(yù)防事故的措施。
15)由主管領(lǐng)導(dǎo)牽頭,檢查預(yù)防事故隱患措施的落實。
16)安全部門要督促用電安全,發(fā)現(xiàn)輕視麻痹思想,要及時進行教育,對違章行
為依據(jù)有關(guān)規(guī)定進行處理。
(8)施工供電系統(tǒng)主要設(shè)備材料見表2-2
表2-2主要設(shè)備材料表
序號名稱規(guī)格型號單位數(shù)量備注
1高壓隔離開關(guān)GW—10—200A臺3
2高壓計量箱10KV、100/5臺1
3電力變壓器S9—600KVA—10/0.4KV臺1
4電力變壓器S9—400KVA—10/0.4KV臺1
5電力變壓器S9—500KVA—10/0.4KV臺1
6柴油發(fā)電機160KW.0.4KV臺2
7柴油發(fā)電機160KW、0.4KV臺2
8功率補償柜BJ(F)—3Z系列臺(套)3
9氧化鋅避雷針HY5WS2—17/50組3
10跌落式開關(guān)RW3—10/100組3
11橡套電纜yc-3*95+1*50km1
1210KV架空線路LGJ-3*35km1
13照明架空線路BLV2*25km1
14照明燈具馬路彎燈套100
15自鎮(zhèn)汞燈250w只500
16油炸木桿7m根100
2.3.2施工供水
(1)施工用水
根據(jù)招標(biāo)文件提供的資料顯示,本工程屬于擴建工程,所以施工供水使用潛水泵
直接抽取原庫區(qū)蓄水的供水方式,即可滿足施工用水的需要。
(2)生活用水
施工輔助作業(yè)區(qū)主要用水有混凝土預(yù)制件廠和機械修配廠,按照預(yù)制件廠生產(chǎn)能
力統(tǒng)計,每天耗水量210mYd,機械修配廠耗水量約50m'/cl,木材加工廠和鋼筋加工廠
用水量很少,約30m'/d,整個施工輔助企業(yè)總耗水量為290m7do
生活供水按《水利水電施工組織設(shè)計手冊》有關(guān)生活用水標(biāo)準(zhǔn)給定的數(shù)據(jù)考慮。
生活用水主要為日常生活用水、食堂飲食用水、浴池用水等三部分。
用水人員按500人/d考慮。
各種用水量計算如下:
日常用水量按“第三類”“第一區(qū)”標(biāo)準(zhǔn),取120L/(人.d)
120LX500人=60m7d
食堂用水按100L/(人.d)
100LX500人=50m7d
洗浴用水按60L/(人.d)
60LX500人=30m3/d
總用水量:60m3+50m3+30=140m3
綜合施工輔助企業(yè)區(qū)和生活區(qū)用水量考慮,在生活營區(qū)附近位置打一口深10米滲
井,襯直徑3000mm水泥管,安裝兩臺揚程40m,流量為30m:'/h,電機容量7.5KW潛水
泵,潛水泵可單臺運行也可兩臺同時運行。在229米高程左右建一座80m3蓄水池,潛
水井泵將水送到此處凈化處理,凈化后的水必須送當(dāng)?shù)匦l(wèi)生防疫部門化驗,合格后方
可飲用。
施工供水主要材料設(shè)備見表2-3o
表2-3供水系統(tǒng)主要材料、設(shè)備
序號名稱規(guī)格型號單位數(shù)量備注
1潛水泵QS20-50/2-5.5臺6作業(yè)區(qū)供水
2潛水泵QS30-40/4-7.5臺2生產(chǎn)、生活區(qū)
3塑料管3寸米600作業(yè)供水管線
4塑料管2寸米600作業(yè)供水管線
5膠皮管1.5寸米200供水管線
6塑料管1.5寸米50供水管線
7鋼管DN80米800生產(chǎn)、生活區(qū)供水管線
8水泥預(yù)制涵管63000mm節(jié)2做滲井用
9挖滲井個2
2.3.3施工供風(fēng)
根據(jù)石方開挖強度確定供風(fēng)設(shè)備設(shè)置方案,滿足最大施工用風(fēng)的要求,滿足安全
運行的要求。明挖施工作業(yè)面要注意防炮、避炮以及影響交通和正常施工等問題。
本工程石方開挖量有2.955萬左右,計劃使用2臺VHP700型移動式柴油空氣壓
縮機
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 職高解剖考試題及答案
- 寧夏美術(shù)面試題及答案
- 聯(lián)邦快遞面試題及答案
- 施工現(xiàn)場安全組織和管理考題及答案
- 常見化學(xué)實驗危害及應(yīng)對措施試題及答案
- 教師如何通過反思完善教育教學(xué)評價體系試題及答案
- 晉城初三試題數(shù)學(xué)及答案
- 智能制造在新能源汽車中的應(yīng)用試題及答案
- 河北會考英語試題及答案
- 小學(xué)教師教育教學(xué)反思的方法探討試題及答案
- 高中英語-英語說課
- 聯(lián)想EAP案例分析
- 社會工作介入老年社區(qū)教育的探索
- 國開電大-工程數(shù)學(xué)(本)-工程數(shù)學(xué)第4次作業(yè)-形考答案
- 高考倒計時30天沖刺家長會課件
- 施工項目現(xiàn)金流預(yù)算管理培訓(xùn)課件
- 時行疾?。ㄖ嗅t(yī)兒科學(xué)課件)
- 街道計生辦主任先進事跡材料-巾幗弄潮顯風(fēng)流
- GB/T 32616-2016紡織品色牢度試驗試樣變色的儀器評級方法
- 部編版小學(xué)語文三年級下冊第七單元整體解讀《奇妙的世界》課件
- 管道支吊架培訓(xùn)教材課件
評論
0/150
提交評論