版權(quán)說明:本文檔由用戶提供并上傳,收益歸屬內(nèi)容提供方,若內(nèi)容存在侵權(quán),請進(jìn)行舉報或認(rèn)領(lǐng)
文檔簡介
XX特大橋連續(xù)剛構(gòu)專項(xiàng)施工方案
XXXXXXXXXX高速鶴峰東段土建二標(biāo)項(xiàng)目經(jīng)理部
2021年11月
XX特大橋連續(xù)剛構(gòu)專項(xiàng)施工方案
編制:_______________________
審核:_______________________
審批:_______________________
XXXXXXXXXX高速鶴峰東段土建二標(biāo)項(xiàng)目經(jīng)理部
2021年11月
XXXXXXX高速公路鶴峰東段土建二標(biāo)XX大橋連續(xù)剛構(gòu)專項(xiàng)施工方案
目錄
第一章編制說明................................................1
1.1編制范圍................................................1
1.2編制依據(jù)................................................1
1.3編制原則................................................1
第二章工程概況.................................................2
2.1工程簡介................................................2
2.1.1總體工程概況.....................................2
2.1.2xx特大橋連續(xù)剛構(gòu)懸臂澆筑工程概況.................2
2.2自然條件...............................................4
2.2.1地形、地貌........................................4
2.2.2地質(zhì)構(gòu)造..........................................4
2.2.3地層巖性..........................................5
2.2.4水文..............................................5
2.2.5地震動峰值加速度..................................6
2.2.6氣象..............................................6
2.3工程數(shù)量................................................7
第三章施工部署.................................................8
3.1施工場地布置及施工便道..................................8
3.2施工塔吊..............................................10
3.3施工升降梯.............................................II
3.4施工用電用水...........................................12
3.4.1施工用電.........................................12
3.4.2施工用水.........................................13
3.5鋼筋加工廠............................................13
3.6鋼結(jié)構(gòu)加工廠...........................................14
3.7混凝土生產(chǎn)、運(yùn)輸、澆筑方式............................14
XXXXXXX高速公路鶴峰東段土建二標(biāo)XX大橋連續(xù)剛構(gòu)專項(xiàng)施工方案
3.7.1混凝土攪拌站.....................................14
3.7.2澆筑方式.........................................15
3.8資源配置...............................................15
3.8.1人力資源配置.....................................15
3.8.2施工機(jī)械及設(shè)備配置...............................16
3.9工期計劃...............................................17
第四章主要施工方案............................................18
4.1總體施工方案..........................................18
4.2施工工藝流程..........................................19
4.30#塊施工...............................................20
4.3.10#塊概述.........................................20
4.3.2施工工藝流程.....................................21
4.3.3托架制作、安裝...................................22
4.3.4托架預(yù)壓.........................................25
4.3.5模板工程.........................................28
4.3.6鋼筋及預(yù)應(yīng)力管道安裝.............................30
4.3.7混凝土澆筑.......................................31
4.3.8預(yù)應(yīng)力施工.......................................32
4.4持篇安裝、預(yù)壓........................................33
4.4.1掛籃結(jié)構(gòu).........................................33
4.4.2掛籃拼裝.........................................36
4.4.3掛籃拼裝、使用注意事項(xiàng)...........................39
4.4.4掛籃預(yù)壓試驗(yàn).....................................39
4.4.5掛籃試走行.......................................43
4.4.6掛籃走行.........................................44
4.4.7掛籃拆除.........................................45
4.5掛籃懸澆施工...........................................45
4.5.1掛籃懸澆施工流程.................................45
4.5.2模板工程.........................................46
2
XXXXXXX高速公路鶴峰東段土建二標(biāo)XX大橋連續(xù)剛構(gòu)專項(xiàng)施工方案
4.5.3鋼筋、預(yù)應(yīng)力安裝.................................48
4.5.4混凝土澆筑.......................................51
4.5.5預(yù)應(yīng)力張江錨固壓漿...............................54
4.5.6施工監(jiān)測.........................................57
4.5.7連續(xù)梁掛籃施工安全防護(hù)...........................59
4.6邊跨現(xiàn)澆直線段施工.....................................60
4.7合攏段施工............................................66
4.8掛籃防護(hù)..............................................78
4.8.1掛籃兜底防護(hù).....................................78
4.8.2平臺、通道、臨邊防護(hù).............................79
第五章冬季、雨季及高溫施工措施.............................82
5.1冬季施工..............................................82
5.1.1鋼筋的焊接及預(yù)應(yīng)力筋施工.........................82
5.1.2混凝土配制和攪拌.................................82
5.1.3混凝土運(yùn)輸和澆筑.................................82
5.1.4混凝土養(yǎng)護(hù).......................................83
5.1.5混凝土模板.......................................83
5.1.6冬季施工混凝土質(zhì)量檢查...........................83
5.1.7冬季混凝土施工設(shè)備保養(yǎng)措施.......................83
5.2雨季施工..............................................84
5.2.1雨季施工安排.....................................84
5.2.2鋼筋、模板工程...................................84
5.2.3混凝土工程.......................................84
5.2.4高空作業(yè).........................................85
5.2.5材料存放.........................................85
5.2.6環(huán)境保護(hù)措施.....................................85
5.2.7用電安全等其它措施...............................85
5.2.8其他注意事項(xiàng).....................................86
5.3夏季施工...............................................87
3
XXXXXXX高速公路鶴峰東段土建二標(biāo)XX大橋連續(xù)剛構(gòu)專項(xiàng)施工方案
5.3.1混凝土配制和攪拌.................................87
5.3.2混凝土運(yùn)輸及澆筑.................................87
5.3.3混凝土的養(yǎng)護(hù).....................................88
5.4其他方面..........................................88
第六章質(zhì)量保證措施...........................................89
6.1質(zhì)量管理組織機(jī)構(gòu)......................................89
G.2質(zhì)量管理制度...........................................92
6.2.1工程質(zhì)量例會制度................................92
6.2.2工程測量制度....................................92
6.2.3培訓(xùn)、教育制度..................................92
6.2.4工程材料、設(shè)備構(gòu)配件進(jìn)場檢驗(yàn)制度................92
6.2.5作業(yè)指導(dǎo)書編制制度..............................92
6.2.6施工圖會審制度..................................92
6.2.7施工技術(shù)交底制度................................92
6.2.8專項(xiàng)施工方案評審制度............................93
6.2.9開工報告制度....................................93
6.2.10自檢、互檢和交接檢查制度.......................93
6.2.11首件工程驗(yàn)收制度...............................93
6.2.12工序交接及隱蔽工程、關(guān)鍵部位椅杳驗(yàn)收制度......93
6.2.13不合格產(chǎn)品處理制度.............................93
6.2.14成品保護(hù)制度...................................93
6.2.15質(zhì)量事故報告、調(diào)查和處理制度...................94
6.2.16質(zhì)量保證體系運(yùn)行例會制度.......................94
6.2.17工程質(zhì)量獎懲制度...............................94
6.2.18施工技術(shù)資料(檔案)管理制度...................94
6.3施工保證措施..........................................94
6.3.1工藝措施控制.....................................94
6.3.2工序質(zhì)量控制措施.................................94
6.4技術(shù)保證措施.........................................100
4
XXXXXXX高速公路鶴峰東段土建二標(biāo)XX大橋連續(xù)剛構(gòu)專項(xiàng)施工方案
6.4.1崗前培訓(xùn)教育.....................................100
6.4.2作業(yè)指導(dǎo)書編制、技術(shù)交底........................100
6.4.3工序檢查制度.....................................100
6.4.4獎懲措施........................................10()
6.4.4設(shè)備維修保養(yǎng)....................................101
6.5質(zhì)量驗(yàn)收標(biāo)準(zhǔn)..........................................101
6.6工程質(zhì)量通病及防治措施.................................106
6.6.1鋼筋工程........................................106
6.6.2混凝土工程......................................108
6.6.3預(yù)應(yīng)力工程......................................109
第七章安全保證措施..........................................112
7.1安全管理機(jī)構(gòu)..........................................112
7.1.1安全生產(chǎn)領(lǐng)導(dǎo)小組職責(zé)...........................112
7.2安全保證體系..........................................113
7.3安全管理責(zé)任制........................................115
7.3.1項(xiàng)目經(jīng)理安全管理職責(zé)............................115
7.3.2項(xiàng)目書記安全管理職責(zé)............................115
7.3.3總工程師安全管理職責(zé)............................116
7.3.4生產(chǎn)副經(jīng)理安全管理職責(zé)..........................116
7.3.5副總工程師安全管理職責(zé)..........................117
7.3.6安全總監(jiān)安全管理職責(zé)............................117
7.3.7安全部部長安全管理職責(zé)..........................117
7.3.8質(zhì)量部長安全管理職責(zé)............................118
7.3.9工程部部長安全管理職責(zé)..........................118
7.3.10物機(jī)部部長安全管理職責(zé).........................119
7.3.11總經(jīng)濟(jì)師安全管理職責(zé)...........................119
7.3.12綜合辦公室主任安全管理職責(zé).....................120
7.3.13試驗(yàn)室主任安全管理職責(zé).........................120
7.3.14測量組長安全管理職責(zé)...........................120
5
XXXXXXX高速公路鶴峰東段土建二標(biāo)XX大橋連續(xù)剛構(gòu)專項(xiàng)施工方案
7.3.15安全員安全管理職責(zé)............................121
7.3.16技術(shù)員安全管理職責(zé)............................121
7.3.17作業(yè)隊(duì)長安全管理職責(zé)..........................121
7.3.18作業(yè)隊(duì)伍技術(shù)負(fù)責(zé)人安全管理職責(zé)................122
7.3.19班組長安全管理職責(zé)............................122
7.3.20作業(yè)人員安全生產(chǎn)職責(zé)安全管理職責(zé)..............123
7.4安全制度保證措施......................................123
7.4.1安全生產(chǎn)獎罰規(guī)定與基本原則.....................123
7.4.2安全生產(chǎn)獎勵...................................124
7.4.3安全生產(chǎn)處罰...................................124
7.4.4安全生產(chǎn)獎罰的執(zhí)行............................126
7.5安全教育保證措施......................................126
7.5.1教育和培訓(xùn)時間..................................127
7.5.2教育和培訓(xùn)的形式與內(nèi)容..........................127
7.5.3培訓(xùn)效果檢查....................................128
7.6安全技術(shù)保證措施......................................129
7.6.1防止掛籃傾覆保證措施............................129
7.6.2起重吊裝施工安全保證措施........................131
7.6.3臨功防護(hù)安全保證措施............................132
7.6.4用電作業(yè)和特殊工種的安全保證措施................132
7.6.5防雷擊的對策措施................................133
7.6.6機(jī)械傷害預(yù)防措施................................133
7.6.7鋼筋加工安全措施................................134
7.6.8腳手架安裝及拆除安全措施........................134
7.6.9模板安裝及拆除施工..............................135
7.6.10混凝土澆筑安全措施.............................136
7.6.11高空作業(yè)安全措施...............................136
7.6.12預(yù)應(yīng)力施工安全措施.............................137
7.6.13汛期防護(hù)措施...................................137
6
XXXXXXX高速公路鶴峰東段土建二標(biāo)XX大橋連續(xù)剛構(gòu)專項(xiàng)施工方案
7.6.14掛籃拼裝施工安全措施..........................138
7.6.15掛籃拆除施工安全措施..........................138
第八章安全生產(chǎn)事故應(yīng)急救援..................................140
8.1應(yīng)急組織體系.........................................140
8.2指揮機(jī)構(gòu)及職責(zé)........................................141
8.2.1總指揮(組長)職責(zé).............................141
8.2.2副指揮(副組K)職責(zé)...........................141
8.2.3通訊聯(lián)絡(luò)組職責(zé).................................141
8.2.4技術(shù)支持組職責(zé)................................141
8.2.5現(xiàn)場保衛(wèi)組職責(zé).................................141
8.2.6搶險搶救組職責(zé).................................142
8.2.7醫(yī)療救護(hù)組職責(zé).................................142
8.2.8后勤保障組職責(zé)................................142
8.2.9信息發(fā)布組職責(zé).................................142
8.2.10各施工隊(duì)?wèi)?yīng)急領(lǐng)導(dǎo)小組職責(zé)......................142
8.3應(yīng)急處置..............................................142
8.4保障措施..............................................143
8.4.1通信與信息保障..................................143
8.4.2應(yīng)急隊(duì)任保障....................................143
8.4.3應(yīng)急物資裝備保障................................144
8.4.4經(jīng)費(fèi)保障........................................144
8.4.5交通保障........................................144
8.4.6醫(yī)療保障........................................144
8.4.7治安保障........................................144
8.4.8后勤保障........................................144
8.5后期處置..............................................145
8.5.1善后賠償........................................145
8.5.2污染物處理......................................145
8.5.3事故后果影響消除................................145
7
XXXXXXX高速公路鶴峰東段土建二標(biāo)XX大橋連續(xù)剛構(gòu)專項(xiàng)施工方案
8.5.4生產(chǎn)秩序恢復(fù)...................................145
8.5.5應(yīng)急預(yù)案的修訂................................145
8.6xx特大橋施工安全專項(xiàng)應(yīng)急處置..........................145
8.6.1高處墜落應(yīng)急預(yù)案................................145
8.6.2觸電事故應(yīng)急處置措施............................146
8.6.3機(jī)械傷害、物體打擊應(yīng)急措施......................147
8.7危險因素辨識與分析...................................148
第九章文明施工及環(huán)境保護(hù)....................................150
9.1文明施工、環(huán)境保護(hù)目標(biāo)...............................150
9.2文明施工措施.........................................150
9.2.1文明施工管理措施................................150
9.2.2施工中的文明施工措施............................151
9.3環(huán)境保護(hù)措施..........................................151
9.3.1大氣污染及噪聲污染防治..........................151
9.3.2水污染的防治....................................152
9.3.3防噪音污染......................................152
9.3.4水土保持措施....................................153
8
XXXXXXX高速公路鶴峰東段土建二標(biāo)XX大橋連續(xù)剛構(gòu)專項(xiàng)施工方案
第一章編制說明
1.1編制范圍
本專項(xiàng)施工方案的編制范圍為XX宜都至來鳳高速公路鶴峰東段土建二標(biāo)XX
特大橋連續(xù)剛構(gòu)懸臂澆筑施工。
1.2編制依據(jù)
本施工方案的編制以下列文件和資料為依據(jù):
(1)《公路橋涵施工技術(shù)規(guī)范》(JTG/T3650—2020)
(2)《公路工程質(zhì)量檢驗(yàn)評定標(biāo)準(zhǔn)》(JTGF80/1-2017)
(3)《橋梁懸臂澆筑施工技術(shù)標(biāo)準(zhǔn)》(CJJ281T-2018)
(4)《施工現(xiàn)場臨時用電安全技術(shù)規(guī)范》(JGJ46-2005)
(5)《公路工程施工安全技術(shù)規(guī)范》(JTGF90—2015)
(6)《爆破安全規(guī)程》(GB67222-2014)
(7)《建筑機(jī)械使用安全技術(shù)規(guī)范》(JTJ33-2012)
(8)《中華人民共和國環(huán)境保護(hù)法》
(9)《危險性較大的分部分項(xiàng)工程安全管理規(guī)定》(建辦質(zhì)(2018)31號)
(10)《工程地質(zhì)手冊(第五版)》
(ID《XX宜都至來鳳高速公路鶴峰東段兩階段施工圖設(shè)計》
(12)《xx省高速公路建設(shè)標(biāo)準(zhǔn)化指南》
1.3編制原則
本著安全、優(yōu)質(zhì)、高效、合理的原則,結(jié)合本工程實(shí)際情況,合理選用施工方
法,運(yùn)用項(xiàng)目法施工管理模式,制定切實(shí)可行的施工方案,以質(zhì)量管理為中心,以科
學(xué)管理為手段,精細(xì)管理、嚴(yán)謹(jǐn)施工,爭創(chuàng)精品工程。
XXXXXXX高速公路鶴峰東段土建二標(biāo)XX大橋連續(xù)剛構(gòu)專項(xiàng)施工方案
第二章工程概況
2.1工程簡介
2.1.1總體工程概況
宜來高速公路鶴峰東段為XX省公路水運(yùn)交通運(yùn)輸“十三五”發(fā)展規(guī)劃綱要中
的重要組成部分(以下簡稱“本項(xiàng)目”),也是xx省省道網(wǎng)規(guī)劃綱要(2011-2030年)
的“橫5線”陽新至咸豐高速公路的鶴峰東段。
宜來高速鶴峰東段土建二標(biāo)全長18.2km,標(biāo)段內(nèi)有橋梁、涵洞、隧道和路
基工程,以及改路改河工程,其中橋梁18座,互通式立體交叉1座,隧道2座。
2.1.2xx特大橋連續(xù)剛構(gòu)懸臂澆筑工程概況
XX特大橋位于XX省恩施土家族苗族自治州鶴峰縣燕子鎮(zhèn)XX境內(nèi),路線走向
跨越XX山間斜坡溝谷而建設(shè)。XX特大橋連續(xù)剛構(gòu)跨度采用
65m+i20m+65m,采用雙幅布置。主墩承臺采用矩形承臺,承臺尺寸為10.5X10.5
X4.5m,每個承臺下布置4根62.5m嵌巖樁,主墩20井墩樁長44m,21#墩樁長
15m。主墩高度為62?66nb主墩截面尺寸為6.0X6.5m。主梁橋面寬12.5m,底
寬為6.5m,懸臂寬度3m,懸臂根部橋面厚度0.7m,懸臂翼緣板厚0.2m。主墩處
梁高7m,跨中梁高3nb頂板厚度0.3m,底板厚度從1.5m?0.32m均勻變化,腹
板厚度有0.5m、0.7m兩種厚度,在9#節(jié)段設(shè)置過渡段均勻變化。0#塊長度13m,
邊跨直線段長度4m,懸澆節(jié)段長度3.5?4.5m,合攏段長度2m,單個掛籃懸澆
13個節(jié)段。箱梁澆筑分段長度依次為:13.0m長0號段+4X3.5m+4X4.0m+5X
4.5m,邊、中跨合攏段均長2.0m,邊跨現(xiàn)澆段長3.84m。1#節(jié)段為懸澆最重節(jié)段,
重量為166.4to
主橋上部結(jié)構(gòu)按全預(yù)應(yīng)力混凝土構(gòu)件設(shè)計,梁體采用三向預(yù)應(yīng)力體系,縱向
和橫向預(yù)應(yīng)力鋼束采用GB/T5224-2O14標(biāo)準(zhǔn)鋼絞線,單根鋼絞線直徑15.2mm,
公稱面積為139mm2,彈性模量1.95xl()5MPa,標(biāo)準(zhǔn)強(qiáng)度1860Mpa,縱向預(yù)應(yīng)力
鋼束設(shè)計錨下張拉控制應(yīng)力采用Geon=0.75fpk。豎向預(yù)應(yīng)力JL32mm精軋螺紋鋼
筋??v、橫向預(yù)應(yīng)力束管道采用預(yù)埋金屬波紋管成孔,豎向預(yù)應(yīng)力束管道采用預(yù)埋
050x1.5鋼管成孔。
2
XXXXXXX高速公路鶴峰東段土建二標(biāo)XX大橋連續(xù)剛構(gòu)專項(xiàng)施工方案
圖2.1?1XX特大橋主橋平面位置圖
圖2.1-1主橋中跨懸澆節(jié)段劃分(單位:cm)
3
XXXXXXX高速公路鶴峰東段土建二標(biāo)XX大橋連續(xù)剛構(gòu)專項(xiàng)施工方案
圖2.1?2主墩處梁截面布置圖(單位:cm)
圖2.1.3跨中截面布置圖(單位:cm)
2.2自然條件
2.2.1地形、地貌
橋址區(qū)屬構(gòu)造剝蝕、溶蝕低中山區(qū),周邊峰頂標(biāo)高約800?960m,山頂渾圓,
山脊狹長。路線跨山間斜坡溝谷而建設(shè),坡面凹凸起伏,地形較緩,自然坡度
30?35。。
2.2.2地質(zhì)構(gòu)造
路線區(qū)地處上楊子臺坪(in1)八面山臺褶帶(n【13)內(nèi)的長陽臺褶束(mi3~3)
內(nèi),位于鶴峰?五峰向斜帶內(nèi),經(jīng)歷多次構(gòu)造變動,構(gòu)造形跡較復(fù)雜,褶皺發(fā)育,
斷裂構(gòu)造不顯。擬建橋址區(qū)出露三疊系下中統(tǒng)嘉陵江組(Tl-2j)灰?guī)r,巖層產(chǎn)
狀為268。N49。。區(qū)內(nèi)巖體主要有三組節(jié)理,產(chǎn)狀:77。/36。、323。/54。、
4
XXXXXXX高速公路鶴峰東段土建二標(biāo)XX大橋連續(xù)剛構(gòu)專項(xiàng)施工方案
338°Z82°,裂隙主要呈微張?密閉狀,未見充填物。
2.2.3地層巖性
根據(jù)地質(zhì)調(diào)繪和鉆探資料,橋址區(qū)覆蓋層由第四系殘坡積(Qel+dl)含礫粘
土組成;下伏基巖為三疊系下中統(tǒng)嘉陵江組(Tl-2j)灰?guī)r。地層巖性特征如下:
①含礫粘土(Qel+dl):分布于橋位區(qū)斜坡地帶,揭露層厚0.5?5.1m。褐
黃色,稍濕,可塑,土質(zhì)粘性較好,含少量灰?guī)r礫石,巖芯采取率約90%o承載力
基本容許值[fa0]=160kPa,摩阻力標(biāo)準(zhǔn)值qik=50kPao
②巖溶化灰?guī)r(Tl-2j):最大揭露層厚46.2m。淺灰、灰白色,隱晶質(zhì)結(jié)構(gòu),
中厚層狀構(gòu)造,主要礦物成分為白云石及方解石等。巖芯較破碎,多呈短柱狀和
3?9cm碎塊狀,巖質(zhì)硬,錘擊聲脆,巖芯采取率約80%?90%,RQD=IO%o
承載力基本容許值[fa0]=800kPao
③中風(fēng)化灰?guī)r(T1.藥):最大揭露層厚34.4mo淺灰色,隱晶質(zhì)結(jié)構(gòu),中厚
層狀構(gòu)造,主要礦物成分為白云石及方解石等。巖芯較完整,多呈10cm?25cm短
柱狀,局部裂隙發(fā)育,呈3?9cm碎塊狀,巖質(zhì)硬,巖芯采取率約85%?90%,
RQD=50%?80%。承載力基本容許值[fa()]=1000?200()kPa。淺部4m溶隙、溶
溝、溶槽、溶洞發(fā)育,并為粘土充填,灰黃色,稍濕,可塑。部分鉆孔中風(fēng)化灰
巖中夾泥質(zhì)粉砂巖夾層,砂泥質(zhì)結(jié)構(gòu),中薄層狀構(gòu)造,礦物成份主要為石英、長石
及粘土礦物。節(jié)理裂隙發(fā)育,裂面見黑色鐵缽質(zhì)浸染,巖質(zhì)軟,巖心較破碎,多
呈碎塊狀,曝曬后易裂,錘出易碎,巖芯采取率約80%,KQD=0%o承載力基本容
許值[fa0]=600kPao
2.2.4水文
橋址區(qū)無地表水,地下水主要有松散堆積層孔隙滯水及基巖巖溶裂隙水。
孔隙滯水:主要賦存于殘坡積土層孔隙中,含水層厚度變化較大,分布不連
續(xù),處于斜坡地帶,貯水條件較差,僅季節(jié)性有水,水量貧乏?;鶐r巖溶裂隙水:橋
址區(qū)下伏基巖三疊系下中統(tǒng)嘉陵江組(Tl-2j)灰?guī)r,受構(gòu)造影響、風(fēng)化作用影
響,淺部溶蝕裂隙發(fā)育,構(gòu)造及風(fēng)化裂隙帶中含有一定量的基巖裂隙水。該類型地
下水通過大氣降水垂直入滲、上覆土層中的上層滯水下滲補(bǔ)給,沿裂隙以脈狀滲流形
式呈點(diǎn)、線狀向溝谷谷底等地形較低處側(cè)向排泄,受裂隙發(fā)育程度、充填物等因素制
約,該含水層貯水空間有限,分布不均,貯水量小。主墩位于低洼
5
XXXXXXX高速公路鶴峰東段土建二標(biāo)XX大橋連續(xù)剛構(gòu)專項(xiàng)施工方案
地帶,溶洞發(fā)育,溶洞為串珠狀,而且較大,雨季時該處巖溶水較豐富。區(qū)內(nèi)環(huán)境
水質(zhì)較好,對混凝土結(jié)構(gòu)具微腐蝕性,對鋼筋混凝土結(jié)構(gòu)中鋼筋具微腐蝕性。
2.2.5地震動峰值加速度
根據(jù)國家標(biāo)準(zhǔn)《建筑抗震設(shè)計規(guī)范》(GB50011-2010)和《中國地震動參數(shù)區(qū)
劃圖》(GB18306-2015),本區(qū)設(shè)計地震分組為第一組,設(shè)計地震烈度為VI度,設(shè)
計基本地震加速度值為0.05g,特征周期為0.35so依據(jù)交通部頒發(fā)的《公路工程
抗震設(shè)計規(guī)范》規(guī)定,重點(diǎn)橋梁按7度設(shè)防。
路線區(qū)處于新華夏系北東向褶皺和壓扭性斷裂帶內(nèi),區(qū)內(nèi)地震多與北東向斷
裂帶活動有關(guān);地震活動總體具強(qiáng)度弱、頻度低、震源淺特點(diǎn)。鶴峰縣境內(nèi)僅發(fā)
生過2.9級以下的地震。
2.2.6氣象
項(xiàng)目區(qū)屬亞熱帶大陸性季風(fēng)濕潤氣候區(qū),四季分明,春長于秋,夏長于冬,
雨熱同季,光照充足,氣候溫和,雨量充沛,終年濕潤,因地形錯綜復(fù)雜,地勢高
差懸殊,又呈現(xiàn)出極其明顯的氣候垂直地域差異,一般有隨海撥每升高100m,氣
溫下降0.56?0.66C的特征。溫差變化較大的月份為7、8兩月,溫差變化較大
的地區(qū)為狹谷盆地區(qū),極端最高氣溫40.8℃,極端最低氣溫?12.7℃。個別地段
因坡向不同也存在氣溫差異,一般是陽坡大于陰坡。境內(nèi)降雨充沛,年平均降雨量
一般在1300-1700mm,每年的1月、2月和12月降雨量最少,一般在30mm以下;
6月和7月降雨量最多,并具降大雨、暴雨的特征,其降雨量一般在200mm左右。熨
季山區(qū)小氣候特征明顯,雷陣雨、暴雨頻繁出現(xiàn),常伴有山洪暴發(fā),并易發(fā)滑坡、
崩塌、泥石流等地質(zhì)災(zāi)害。
區(qū)內(nèi)冬季有寒凍現(xiàn)象發(fā)生,海拔1000m上的中山、高中山區(qū)以上積雪現(xiàn)象
較明顯,海拔1200m以上易結(jié)冰,臨時性凍土厚度一般30cm以內(nèi)。
6
XXXXXXX高速公路鶴峰東段土建二標(biāo)XX大橋連續(xù)剛構(gòu)專項(xiàng)施工方案
2.3工程數(shù)量
擬進(jìn)行上部結(jié)構(gòu)現(xiàn)澆梁主要工程數(shù)量見下表:
表2.3-1上部結(jié)構(gòu)現(xiàn)澆梁主要工程數(shù)量表
材料名稱規(guī)格型號單位數(shù)量
HPB300-16Kg2526.4
HRB400-12Kg247296.3
鋼筋
HRB400-16Kg566880.3
HRB400-20Kg142462.8
混凝土C50m37274.7
鋼板Q235Kg24479.4
<1)32精軋螺紋Kg93741
鋼絞線Kg417454.6
650*1.5鋼管m13296
640波紋管m5120
650波紋管m11711.6
*90波紋管m21193.3
YM15-3錨具套992
預(yù)應(yīng)力材料
YM15-3p錨具套992
YM15-12錨具套144
YM15-15錨具套344
YM15-17錨具套352
YGM錨具張拉套3024
YGM錨具固定套3024
7
XXXXX集團(tuán)宜來高速鶴峰東段土建二標(biāo)XX特大橋連續(xù)剛構(gòu)專項(xiàng)施工方案
第三章施工部署
3.1施工場地布置及施工便道
施工場地利用墩柱及0#塊已有施工布置??紤]左右幅及20#、21#墩頂同時施工,布
置四套菱形掛籃。在右幅20號墩、左幅21#墩外側(cè)各設(shè)置16t塔吊1部,在墩柱上設(shè)置一
道附著;每個墩柱上均設(shè)置1部施工電梯,并設(shè)置電梯安全通道。在墩柱附近設(shè)置材料堆
放和拼裝場地,并給吊車等機(jī)械預(yù)留足夠的擺放空間。施工平面布置如下圖所示,詳見“附件
1:施工平面布置圖”。
圖3.1-1施工現(xiàn)場平面布置示意圖
第8頁
XXXXX集團(tuán)宜來高速鶴峰東段土建二標(biāo)XX特大橋連續(xù)剛構(gòu)專項(xiàng)施工方案
214228里宣工平山布R圖產(chǎn)
n
■?
□:
7
5—3
圖3.1-221#墩、22#墩施工平面布置圖(單位:m)
圖3.L319#墩、20#墩施工平面布置圖(單位:m)
第9頁
XXXXX集團(tuán)宜來高速鶴峰東段土建二標(biāo)XX特大橋連續(xù)剛構(gòu)專項(xiàng)施工方案
本橋懸臂梁施工利用既有鄉(xiāng)道B2T(2#主便道)到達(dá)施工點(diǎn)位,鄉(xiāng)道無法到達(dá)工點(diǎn)
修建支線便道到達(dá)工點(diǎn)。支線便道路基寬7.5m,路面寬7m,使用C20混凝土硬化20cm。
進(jìn)場道路布置見下圖“圖3.1?4進(jìn)場道路布置圖工
圖3.1?4進(jìn)場道路布置圖
32施工塔吊
根據(jù)墩柱施工需要,主墩(20#、21#)塔吊型號為TC7530(65M臂長),臂長(作業(yè)半
徑)為65m,最大起重量為16t,基本參數(shù)見下表:
表321塔吊基本參數(shù)表
塔吊基本參數(shù)
塔吊型號TC7530額定起重力矩315t*m最大起重量16t
最終安裝高度80.4m安裝臂長60m起重臂吊點(diǎn)26.9m
吊鉤工作幅度2.5%0m標(biāo)準(zhǔn)節(jié)尺寸(m)2.1X2.11X3.306附著道數(shù)1
塔吊TC7530吊裝性能見“表3.2-2TC753060m臂長起重性能特性表”。作業(yè)半徑小
于等于47.5m時,二倍率條件下吊裝能力大于等于6t,能夠滿足墩柱施工所有工況條件下
最大吊裝荷載需求。
第10頁
XXXXX集團(tuán)宜來高速鶴峰東段土建二標(biāo)XX特大橋連續(xù)剛構(gòu)專項(xiàng)施工方案
表3.2-2TC753060m臂長起重性能特性表
幅度(m)4.0-19.420.022.525.027.530.032.535.037
二倍率(t)8.0
四倍率(t)16.015.413.411.810.69.58.67.87.3
幅度(m)40.042.545.047.550.052.555.057.560.0
二倍率⑴7.36.86.46.05.65.35.04.74.5
四倍率⑴6.66.15.75.34.94.64.34.03.8
過渡墩(19#、22#)塔吊型號為T7020-12E(60M臂長),臂長(作業(yè)半徑)為60m,
最大起重量為12t,性能參數(shù)見下表:
表3.2-3T7020-12E60m臂長起重性能特性表
幅度(m)3.5?17.75|20|25|30|34.203540455055
a=26.005.844.984.323.793.36
吊重(t)
a=412.00|10.42|7.95|6.33|5.745.184.323.663.132.70
幅度(m)60
a=2
吊重⑴3.00
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 食堂bot合作模式合同協(xié)議
- 門禁采購協(xié)議書范本
- 面包糕點(diǎn)店鋪轉(zhuǎn)讓合同協(xié)議
- 門店裝修投產(chǎn)合同協(xié)議
- 露營床墊出租合同協(xié)議
- 鞋模具加工合同協(xié)議
- 集體土地承租合同協(xié)議
- 門窗銷售合同協(xié)議模板
- 集裝箱合同協(xié)議模板
- 食品類免責(zé)合同協(xié)議
- 對接焊縫角焊縫的構(gòu)造和計算
- 山東春季高考土建專業(yè)2023年高考題
- 材料力學(xué)(劉鴻文版)學(xué)習(xí)通課后章節(jié)答案期末考試題庫2023年
- 滯期費(fèi)速遣費(fèi)的計算
- 省級特色專業(yè)安徽省高等學(xué)校質(zhì)量工程項(xiàng)目進(jìn)展報告
- 電鍍鉻作業(yè)指導(dǎo)書