某地塊商住樓項目施工組織設(shè)計范本
第一章工程概況.....................................................................6
一、工程概況................................................................6
1、項目名稱及有關(guān)單位...................................................6
2、建筑概況..................................................................6
3、建筑裝飾:................................................................6
4、結(jié)構(gòu)概況..................................................................7
二、編制根據(jù)................................................................7
三、工程特點及施工條件......................................................8
1、工程特點及難點............................................................8
2、施工條件..................................................................8
第二章施工總體部署................................................................10
一、施工總目標(biāo)..............................................................10
1、工期目標(biāo).............................................................10
2、質(zhì)量目標(biāo).............................................................10
3、安全文明施工目標(biāo).....................................................10
二、施工準備................................................................10
1、施工準備工作計劃.....................................................10
2、技術(shù)準備.............................................................10
3、物質(zhì)條件及生產(chǎn)準備...................................................10
4、施工組織準備.........................................................10
5、現(xiàn)場施工準備.........................................................11
三、施工總體順序............................................................11
四、施工進度計劃............................................................II
五、項目組織機構(gòu)............................................................12
1、各管理網(wǎng)絡(luò)...........................................................12
2、保證項目經(jīng)理及項目部成員常駐施工現(xiàn)場...............................15
3、項目部管理人員職責(zé)..................................................15
六、勞動力組織.............................................................20
1、各階段要緊工種勞動力配備計劃.....................................20
2各階段要緊工種勞動力配備計劃表......................................20
七、要緊施工機械投入.......................................................21
1要緊施工機械及計量儀器的選擇與配置.................................21
2、工程要緊施工機械設(shè)備...............................................21
八、現(xiàn)場平面布置...........................................................22
第三章要緊分部分項工程施工方法...................................................28
一、測量定位放線............................................................28
1、定位、布網(wǎng)原則.......................................................28
2、平面操縱網(wǎng)的測設(shè)....................................................28
4、垂直操縱點的設(shè)置、轉(zhuǎn)換及測量方法...................................28
5、標(biāo)高測量操縱........................................................28
二、基坑支護................................................................29
三、土方工程...............................................................28
四、地下室及高層基礎(chǔ)鋼筋碎工程.............................................29
1、基礎(chǔ)底板鋼筋碎工程..................................................29
2、地下室車庫墻板頂板鋼筋碎工程.......................................32
3、回填土工程.........................................................35
六、上部主體結(jié)構(gòu)工程........................................................35
1、施工部置...........................................................35
2、施工工藝流程........................................................36
3、主體結(jié)構(gòu)模板工程...................................................36
4、主體結(jié)構(gòu)鋼筋工程...................................................38
5、土建與安裝配合.....................................................39
6、混凝土的施工.......................................................40
7、砌體砌塊工程.......................................................42
七、屋面工程................................................................44
1、施工做法及順序.....................................................44
2、屋面施工要緊方法...................................................44
八、外腳手架工程............................................................45
1腳手架方案的選型.....................................................45
2腳手架的材料選擇與質(zhì)量標(biāo)準...........................................46
3.懸挑腳手架的搭設(shè)...................................................46
4.腳手架的使用規(guī)定:.................................................50
5.腳手架拆除方案.....................................................51
6腳手架搭設(shè)與構(gòu)造要求.................................................52
7.腳手架的安全措施:...................................................52
九、裝飾工程................................................................53
1、裝飾施工管理要點.....................................................53
2、施工流程............................................................54
3、裝飾施工安排........................................................54
4、門窗安裝施工........................................................54
5、外墻保溫粉刷施工.....................................................55
6、內(nèi)墻粉刷施工........................................................56
7、細石混凝土樓地面施工................................................56
8、內(nèi)、外墻涂料施工....................................................57
十、水、電安裝工程.........................................................58
1、水電安裝工程要緊施工流程.............................................58
2、管道部分要緊施工方法.................................................60
3、衛(wèi)生潔具.............................................................62
4、電氣安裝工程施工方法與技術(shù)措施......................................63
5、風(fēng)管制作安裝.........................................................66
第四章施工難點施工方法............................................................68
一、深基坑施工.............................................................68
1、基坑降水............................................................68
二、基礎(chǔ)回填土.............................................................69
1、回填條件:...........................................................69
2、技術(shù)措施................................................................69
三、填充墻防裂措施............................................................69
1、技術(shù)措施................................................................69
四、屋面防水層施工............................................................70
1、施工工藝流程:..........................................................70
2、混凝土基層處理:........................................................70
3、隔氣層:................................................................70
4、保溫板安裝..............................................................70
5、防水膠膜粘貼............................................................71
第五章施工進度計劃及工期保證措施.....................................................73
一、施工進度計劃.............................................................73
1、施工節(jié)點計劃............................................................73
2、施工進度計劃表..........................................................73
二、工期保證措施.............................................................73
1組織保證措施............................................................73
2技術(shù)保證措施.............................................................75
3勞力保證措施............................................................75
4機械保證措施.............................................................76
5周轉(zhuǎn)材料保證措施.........................................................76
第六章質(zhì)量保證措施...................................................................77
一、質(zhì)量目標(biāo)...................................................................77
二、質(zhì)量保證體系...............................................................77
1質(zhì)量保證體系框圖.........................................................77
2組織管理保證措施.........................................................77
三、各分部分項工程質(zhì)量保證措施................................................78
1、鋼筋工程質(zhì)量保證措施.......................................................78
2、模板工程質(zhì)量保證措施....................................................79
3、砂工程質(zhì)量保證措施.....................................................80
4、砌筑工程技術(shù)質(zhì)量操縱措施...............................................80
5、住宅工程質(zhì)量驗收的應(yīng)用及裝飾施工技術(shù)質(zhì)量操縱措施......................81
6、屋面防水工程施工技術(shù)質(zhì)量操縱措施.......................................81
7、安裝工程質(zhì)量保證措施....................................................81
四、質(zhì)量通病的處理與預(yù)防......................................................82
1鋼筋銹蝕混料堆放.........................................................82
2鋼筋保護層不準...........................................................82
3模板上口不直,寬度不準,麻面等缺陷......................................82
4板模中部下?lián)?,板底混凝土面不平?........................................82
5縫隙夾層..................................................................83
6砌體砂漿強度達不到設(shè)計要求與磚縫砂漿不飽滿..............................83
7內(nèi)墻面抹灰防空鼓、裂縫:.................................................83
8外墻防滲:...............................................................83
9衛(wèi)生間墻根、立管四周滲漏.................................................85
10泥地面防起砂、開裂......................................................86
11窗安裝防滲漏.............................................................86
12油漆防流墜、起皺、透底、倒光、表面粗糙、紋路不清.......................87
13給排水管安裝.............................................................88
14電氣安裝................................................................88
15屋面滲漏防治.............................................................90
16現(xiàn)澆樓板、陽角、轉(zhuǎn)角處裂縫防治..........................................91
17地下室滲漏防治..........................................................91
五、機電安裝質(zhì)量操縱要點......................................................93
六、季節(jié)性施工質(zhì)量管理措施....................................................94
1雨季施工措施..............................................................94
2暑季及臺風(fēng)季節(jié)施工.......................................................94
3冬季施工措施..............................................................95
七、質(zhì)量文件歸檔管理...........................................................97
1、項目經(jīng)理部建立信息情報室:.............................................97
2、施工期間管理:..........................................................97
3、竣工移交資料:..........................................................97
第七章安全保證措施..................................................................98
—安全保證體系及措施.........................................................98
1安全生產(chǎn)的方針、原則與管理目標(biāo).........................................98
2建立現(xiàn)場安全組織機構(gòu)及體系...............................................98
二、建立安全生產(chǎn)責(zé)任制.......................................................99
三、安全生產(chǎn)技術(shù)管理..........................................................99
1安全技術(shù)施工組織設(shè)計.....................................................99
2安全技術(shù)交底及安全教育..................................................99
四、安全保證措施.............................................................100
1基坑開挖工程............................................................100
2、鋼筋加工安全技術(shù)措施...................................................100
3、模板施工安全措施.......................................................100
4混凝土施工安全措施......................................................101
5、高處作業(yè)安全技術(shù)措施...................................................101
6、機械設(shè)備安全技術(shù)措施...................................................101
7、臨時用電安全技術(shù)措施...................................................102
8、保證消防安全的技術(shù)措施.................................................103
9、防臺、防汛措施.........................................................103
10、應(yīng)急預(yù)案..............................................................104
第八章文明施工......................................................................105
一、文明施工管理目標(biāo)........................................................105
二、文明施工措施.............................................................105
1文明施工組織管理措施.................................................105
2、工地文明建設(shè)措施......................................................106
3、場容場貌文明管理措施.................................................106
三、現(xiàn)場圍擋..................................................................107
四、操縱楊塵..................................................................107
五、治污減排.................................................................108
六、降低噪音..................................................................109
第九章季節(jié)施工措施...............................................................110
一、冬季施工技術(shù)措施.......................................................110
二、雨季及汛季施工技術(shù)措施(汛季防洪措施)................................111
三、夏天高溫季施工技術(shù)措施................................................111
第十章成品保護措施...............................................................113
一、成品保護責(zé)任及管理措施................................................113
二、要緊施工項目成品保護...................................................114
1測量定位:...........................................................114
2土方工程:...........................................................114
3地下防水工程..........................................................114
4?感肚工程:..........................................................114
5砌筑工程:...........................................................114
6地面與樓地面工程......................................................115
7門窗工程..............................................................115
8墻、頂棚涂料..........................................................116
9屋面工程..............................................................116
三、交叉施工原則及措施.....................................................116
1要緊工序交叉施工原則及措施..........................................116
2要緊分部工程施工工序................................................117
第十一章、節(jié)能保溫.........................................................119
一、II型發(fā)泡水泥保溫板外保溫墻面
..............................................................................................................................................116
二、斷熱鋁合金框Low-E中空玻璃
..............................................................................................................................................130
三、屋面保溫施工方案
..............................................................................................................................................140
四、節(jié)能工程驗收
...............................................................................................................................................117
第一章工程概況
一、工程概況
1、項目名稱及有關(guān)單位
1.1工程名稱:頤與花園西側(cè)地塊一商住樓項目
1.2工程地址:孩兒巷東側(cè)、頤與花園西側(cè)
1.3建設(shè)單位:江蘇啟秀置業(yè)集團有限公司
1.4監(jiān)理單位:
1.5設(shè)計單位:南通市建筑設(shè)計研究院有限公司
1.6勘察單位:南通市建筑設(shè)計研究院有限公司
L7質(zhì)監(jiān)單位:南通市質(zhì)監(jiān)站
1.8安監(jiān)單位:南通市安監(jiān)站
2、建筑概況
江蘇啟秀置業(yè)集團有限公司擬建頤與花園西側(cè)地塊一商住樓項目位于南通市
孩兒巷北路東側(cè)、頤與花園西側(cè)。該項目建筑用地面積4034m2,總建筑面積約
7500m2o其中地下935平方米。
該項目包含1、2#住宅樓(7-9層)、商業(yè)用房(2層),框架結(jié)構(gòu)。地下一層,
地上七~九層,建筑高度34.8米。
3、建筑裝飾:
墻體:外填充墻為200厚砂加氣碎砌塊,內(nèi)隔墻為200-100厚加氣碎砌塊。
屋面:1、平屋面
①50厚C30細石混凝土”4@150雙向鋼筋,設(shè)分倉縫《6m
②3厚1:3石灰黃砂粉刷隔離層
③20厚1:3水泥砂漿找平層
④二道DWD高分子防水卷材(每道不小于1.2厚)
⑤35厚復(fù)合擠塑聚苯板(A級)
⑥20厚1:2.5水泥砂漿找平層
⑦NZL輕質(zhì)粒找坡(2%),最薄處60厚
⑧現(xiàn)澆鋼筋混凝土屋面板
1、坡屋面
①淺灰色彩瓦
②50厚C20細石混凝土層
③35厚復(fù)合擠塑聚苯板保溫層(A級)
④K11型防水涂膜層一道
⑤15厚1:3水泥砂漿找平層
⑥鋼筋混凝土現(xiàn)澆屋面板C20碎椽條
墻面:外墻面真石漆涂料H型發(fā)泡水泥保溫板墻面;
乳膠漆內(nèi)墻面用于住宅、商業(yè)內(nèi)墻面,瓷磚墻面用于廚房、衛(wèi)生間,高
檔墻面磚內(nèi)墻面用于樓梯間、公共走道等部位。
樓地面:地磚樓面,住宅、商業(yè)為帶細石混凝土水泥樓面,廚房、衛(wèi)生間為帶
防水層水泥樓面,機房等為水泥樓面。
頂棚:乳膠漆;兩度膩子。
門窗:外墻門窗1-2層使用玻璃幕墻與斷熱鋁合金窗,3-9層為斷熱鋁合金窗。
玻璃均使用Low-E中空玻璃.無固定遮陽的外窗均鋁合金伸縮式活動遮陽板。
4、結(jié)構(gòu)概況
本工程為鋼筋混凝土框架結(jié)構(gòu)。
二、編制根據(jù)
1、施工圖紙。
2、《建筑工程施工質(zhì)量統(tǒng)一驗收標(biāo)準》、《地基基礎(chǔ)施工質(zhì)量驗收規(guī)范》、《鋼
筋混凝土施工質(zhì)量驗收規(guī)范》、《建筑裝飾裝修施工質(zhì)量驗收規(guī)范》、《建筑地面施
工質(zhì)量驗收規(guī)范》、《給排水施工質(zhì)量驗收規(guī)范》、《建筑電氣工程施工質(zhì)量驗收規(guī)
范》、《通風(fēng)與空調(diào)工程施工質(zhì)量驗收規(guī)范》、《建筑施工扣件式鋼管腳手架安全技
術(shù)規(guī)范》等規(guī)范、標(biāo)準、行業(yè)標(biāo)準、圖集、建筑工程施工質(zhì)量驗收標(biāo)準強制性條
文及安全生產(chǎn)文明施工的有關(guān)規(guī)范標(biāo)準及要求。
3、江蘇省、南通市有關(guān)質(zhì)量與安全的有關(guān)規(guī)定。
4、企業(yè)標(biāo)準:審定的IS09001-2000企業(yè)質(zhì)量標(biāo)準文件及標(biāo)準化管理的有關(guān)
文件:《質(zhì)量保證手冊》、《管理程序文件》與《作業(yè)指導(dǎo)書》。
三、工程特點及施工條件
1、工程特點及難點
本工程現(xiàn)場東西的中部有一條老人防通道斜穿整個工程的南北方向,對本工
程的基礎(chǔ)工程的施工帶來許多意想不到的不便,基礎(chǔ)開挖時,靠近人防部分,要
多采取人、機配合的施工方法,保護好此人防通道不被破壞。
人防通道部分的基礎(chǔ)處理應(yīng)會同設(shè)計、業(yè)主、監(jiān)理、施工單位共同會簽,拿
出切實可行的施工方案,保證工程的順利進行。
本工程在地下室的東邊,緊靠地下室有一熱氣管穿過本工地,施工時要特別
小心,挖土?xí)r,要做好標(biāo)志由專人監(jiān)護,保證安全施工,不出任何差錯。
本工程現(xiàn)場地勢狹小,給水平運輸帶來了不便?,F(xiàn)場場地有限,現(xiàn)場不搭辦公
與住宿用房,由業(yè)主就近按排。
本工程處于老城市中心,將注重對渣土、建筑垃圾及污水排放的凈化處理進行
強制管理,保證不污染周邊環(huán)境特別是減少對河道的影響,做好衛(wèi)生防疫工作,應(yīng)
變突發(fā)事件。
本工程工程量較大施工工藝復(fù)雜,且施工工期較短,這增加了現(xiàn)場進度計劃的
安排與施工管理的難度。
本工程基坑開挖深,深基坑的降水,深基坑的支護與土方開挖將是施工難點,
加大基坑安全保障力度。
本工程地下室占地面積較大,為局部地下室一至二層為商業(yè)用房、三層以上為
住宅。這樣1-3層搭設(shè)落地腳手架,4-9使用二次懸挑腳手架。
2、施工條件
通過對工程周圍環(huán)境的察看,施工場地狹小,交通不是很方便,因此設(shè)備、材
料等方面的準備有一定的難度。業(yè)主已提供了電源及水源,現(xiàn)場范圍內(nèi)的生產(chǎn)、生
活用電設(shè)施,我們將自行配置。
施工用電:我單位將從業(yè)主提供的臨時電源處安裝兩只表具(施工與生活分
開),引接電源線至施工用電處。
施工用水:在施工現(xiàn)場內(nèi)設(shè)有水源接口,供水總管徑為DN100,設(shè)水表,我單
位將根據(jù)用水要求沿現(xiàn)場布置水管。
第二章施工總體部署
一、施工總目標(biāo)
1、工期目標(biāo)
總工期目標(biāo):210日歷天(包含一個春節(jié)假期)。
2、質(zhì)量目標(biāo)
質(zhì)量目標(biāo):符合《建筑工程質(zhì)量驗收統(tǒng)一標(biāo)準》GB50300-2001合格標(biāo)準、現(xiàn)行施
工驗收規(guī)范及國家、江蘇省、南通市有關(guān)法律法規(guī)。
3、安全文明施工目標(biāo)
安全文明施工目標(biāo):按照南通市有關(guān)規(guī)定實行文明施工管理,爭創(chuàng)“市級文明
工地”。
二、施工準備
1、施工準備工作計劃
施工準備工作是整個施工生產(chǎn)的前提,根據(jù)本工程的工程內(nèi)容與實際情況由
項目部制定施工的準備計劃。為工程順利進展打下良好的基礎(chǔ)。
2、技術(shù)準備
由于本工程建筑所具有的諸多特點,對施工前的準備工作,務(wù)必細致、認確
實進行,否則會造成人力、物力的浪費。施工準備的范圍能夠根據(jù)不一致的施工
階段劃分。
3、物質(zhì)條件及生產(chǎn)準備
建筑工程施工所需的材料、構(gòu)配件、施工機械品種多、數(shù)量大,保證按計劃
供應(yīng),對整個施工過程舉足輕重,否則直接影響工期、質(zhì)量與成本。
4、施工組織準備
為實現(xiàn)本工程建設(shè)的優(yōu)質(zhì)、高速、安全、文明、低耗的目標(biāo)而奮斗,本工程
使用項目法施工的管理體制。形成有一定權(quán)威性的統(tǒng)一指揮,協(xié)調(diào)方面的關(guān)系,
確保工程按要求順利完成。使用項目管理體制的同時,經(jīng)濟合同手段輔助以部分
行政手段,明確各方面責(zé)、權(quán)、禾h本工程擬實行項目法施工管理,委派我公司
實踐經(jīng)驗豐富與管理水平高的1名同志擔(dān)任項目經(jīng)理,選聘技術(shù)、管理水平高的
技術(shù)人員、管理人員、專業(yè)工長組建項目部。項目管理層由項目經(jīng)理、技術(shù)負責(zé)
人、安全、質(zhì)量、材料、保衛(wèi)、機械與后勤等成員構(gòu)成,在建設(shè)單位、監(jiān)理單位
與公司的指導(dǎo)下,負責(zé)對本工程的工期、質(zhì)量、安全、成本等實施計劃。組織、
協(xié)調(diào)、操縱與決策,對各生產(chǎn)施工要素實施全過程的動態(tài)管理。本工程所需要的
勞動力包含混凝土工、鋼筋工、木工、設(shè)備安裝工、砌筑工、裝修工、腳手工等。
根據(jù)施工進度計劃制定勞動力需求計劃,組織人員進場,安排生活,登記并進行
進場教育。
5、現(xiàn)場施工準備
5.1施工現(xiàn)場操縱網(wǎng)點
會同有關(guān)單位做好現(xiàn)場的移交工作,包含測量操縱點與有關(guān)技術(shù)資料,并復(fù)
核操縱點。根據(jù)給定操縱點測設(shè)現(xiàn)場內(nèi)的永久性標(biāo)樁,并做好保護,作為工程測
量的根據(jù)。
5.2現(xiàn)場“三通一平”
5.2.1施工現(xiàn)場平整
施工現(xiàn)場平整,由土方、樁基施工單位已進場施工。
5.2.2修建現(xiàn)場臨時道路
修筑場內(nèi)臨時道路及硬化碎泵車停靠點,提供材料、人員的交通途徑,臨時
道路全線貫穿,直到加工區(qū)。
5.2.3布置施工現(xiàn)場臨時用水、用電。
三、施工總體順序
總體施工順序:基坑支護~土方開挖一地基基礎(chǔ)工程~上部主體結(jié)構(gòu)鋼筋碎
柱、梁、板及填充墻的施工一上部主體裝飾工程一各施工區(qū)水電安裝工程穿插進行
施工。
四、施工進度計劃
詳見施工進度計劃表(附表一)
五、項目組織機構(gòu)
1、各管理網(wǎng)絡(luò)
1.1項目管理網(wǎng)絡(luò)
項目管理網(wǎng)絡(luò)圖
1.2、創(chuàng)優(yōu)管理網(wǎng)絡(luò)
職責(zé):
1.2.1.負責(zé)施工現(xiàn)場質(zhì)量管理制度的制定與貫徹執(zhí)行。
1.2.2.負責(zé)本工程施工過程的質(zhì)量操縱與管理。
1.2.3.定期組織有關(guān)人員定期或者不定期地對工程質(zhì)量進行檢查,并實行通
報制度。
1.2.4.負責(zé)工程創(chuàng)優(yōu)資料的收集整理,并負責(zé)本工程質(zhì)量等級的申報工作。
1.3.安全生產(chǎn)、文明施工、消防控操縱管理網(wǎng)絡(luò)
職責(zé):
1.3.1.負責(zé)本工程施工期安全生產(chǎn)規(guī)章制度、文明施工管理制度及消防操縱
制度的編制、貫徹、執(zhí)行。
1.3.2.負責(zé)本工程施工過程中有關(guān)操縱措施的制定與實施過程中的檢查。
1.3.3.對施工過程中發(fā)現(xiàn)的安全隱患、消防隱患應(yīng)及時組織力量進行消防,
將事故隱患消滅在萌芽狀態(tài)。
1.3.4.負責(zé)文明工地的申報有關(guān)工作。
1.4.環(huán)保管理網(wǎng)絡(luò)
公司施工管理部
公司施工安全科
項目部
職責(zé):
1.4.1.負責(zé)本工程施工期間的環(huán)境操縱、保護工作。
1.4.2.負責(zé)與南通市環(huán)境保護部門進行聯(lián)絡(luò),解決有關(guān)問題。
1.4.3.負責(zé)有關(guān)環(huán)境保護制度與環(huán)境保護措施的制定。
1.4.4.負責(zé)施工現(xiàn)場的環(huán)境檢測工作。
1.4.5.負責(zé)施工現(xiàn)場環(huán)境檢查督促工作。
2、保證項目經(jīng)理及項目部成員常駐施工現(xiàn)場
2.1確保項目經(jīng)理及項目部成員常駐工地現(xiàn)場,負責(zé)履行工程合同約定的義
務(wù)及目標(biāo)的實現(xiàn)。
2.2確保項目經(jīng)理每周常駐施工現(xiàn)場,項目經(jīng)理、項目技術(shù)負責(zé)人及項目部
成員應(yīng)有準備的按時參加業(yè)主組織的例會。
2.3項目經(jīng)理因事要離開工地現(xiàn)場1天以上時,務(wù)必向業(yè)主及總監(jiān)說明原因
并請假,同時書面指派委托人,得到批準后方可離開工地。
2.4項目經(jīng)理如不遵守上述條款、擅自離開施工現(xiàn)場,愿意同意業(yè)主合同條
款中的有關(guān)處罰條款。
3、項目部管理人員職責(zé)
3.1項目經(jīng)理崗位職責(zé)
3.1.1嚴格遵守國家法律、法規(guī)與公司的各項規(guī)章制度及各項的決定,在公
司領(lǐng)導(dǎo)下,全面負責(zé)項目部的生產(chǎn)、經(jīng)營、材料、設(shè)備、質(zhì)量、安全、財務(wù)等工
作。
3.1.2認真執(zhí)行公司年度經(jīng)營承包合同,全面負責(zé)與建設(shè)單位工程施工合同
的履行。
3.1.3加強生產(chǎn)管理,合理調(diào)配工程施工過程中的勞動力、周轉(zhuǎn)材料、機械
設(shè)備等,協(xié)調(diào)好各方面關(guān)系,妥善解決各工種之間產(chǎn)生的矛盾,采取積極有效措
施,保證均衡生產(chǎn),按時完成工程形象進度。
3.1.4對安全生產(chǎn)負有要緊責(zé)任,保證安全生產(chǎn)所需費用的投入,積極改善
勞動條件,做到文明施工,采取切實可行措施,杜絕死亡與重傷事故的發(fā)生,降
低通常事故頻率,確保安全目標(biāo)實現(xiàn)。
3.1.5加強職工思想與遵章守紀教育,對嚴重違法、違紀、危害工程質(zhì)量與
安全生產(chǎn)的做法進行嚴肅處理;
3.1.6參加由監(jiān)理部門組織的例會,負責(zé)定期向公司傳遞工程施工信息。
3.1.7貫徹落實公司程序文件,履行程序文件規(guī)定的職責(zé),確保質(zhì)量環(huán)境
職業(yè)健康管理體系各個要素的執(zhí)行。
3.1.8在授權(quán)范圍內(nèi),代表公司負責(zé)本處財務(wù)審核、審批、督促財務(wù)部門搞
好財務(wù)核算。
3.2項目副經(jīng)理崗位職責(zé)
3.2.1認真貫徹執(zhí)行國家基本建設(shè)方針、政策,及公司的程序文件,組織與
指揮好施工現(xiàn)場生產(chǎn)與安全防護。
3.2.2執(zhí)行公司年度經(jīng)營承包合同,按時完成工程任務(wù),保證生產(chǎn)計劃的實
施,全面履行工程承包合同,保證各項指標(biāo)實現(xiàn)。
3.2.3抓好施工準備、施工過程、交工驗收等全過程的管理工作,并根據(jù)分
部項工程質(zhì)量需要,合理安排與調(diào)配勞動力、機械、設(shè)備與有關(guān)急需材料,做好
本項目部生產(chǎn)計劃調(diào)度安排工作。
3.2.4配合項目經(jīng)理做好項目部各項工作,當(dāng)項目經(jīng)理不在時,代替項目經(jīng)
理行使其有關(guān)職責(zé)。
3.2.5負責(zé)職工隊伍建設(shè)、提高隊伍的思想、文化、技術(shù)素養(yǎng)。
3.2.6負責(zé)協(xié)助做好施工現(xiàn)場材料管理。
3.3項目技術(shù)負責(zé)人崗位職責(zé)
3.3.1負責(zé)項目施工組織設(shè)計、分部工程施工方案、作業(yè)指導(dǎo)書、不合格品
的返修方案等的編制。
3.3.2審核工程資料、審批項目部技術(shù)性文件及發(fā)放范圍,對項目部的技術(shù)
工作負總責(zé)。
3.3.3負責(zé)運用與推廣新技術(shù)、新材料、新工藝,積極開展技術(shù)革新活動與
QC小組活動;負責(zé)“四新”技術(shù)應(yīng)用情況總結(jié)。
3.3.4負責(zé)各項技術(shù)交底工作,參加圖紙會審與工程例會。
3.3.5負責(zé)項目部的各項技術(shù)培訓(xùn),組織項目部進行各項技術(shù)比武。
3.3.6參加主管部門與業(yè)主等組織的各項技術(shù)會議與培訓(xùn),參加各類技術(shù)交
流。
3.4施工員崗位職責(zé)
3.4.1認真貫徹執(zhí)行國家法律法規(guī)與公司各項規(guī)章制度。
3.4.2刻苦學(xué)習(xí)與鉆研業(yè)務(wù)知識,努力提高業(yè)務(wù)素養(yǎng)與自身行為素養(yǎng)。
3.4.3參加圖紙會審、設(shè)計交底、技術(shù)復(fù)核、分部分項驗收及竣工驗收。
3.4.4負責(zé)分項工程開工前向作業(yè)班組長進行施工與環(huán)保方面技術(shù)交底,負責(zé)
施工現(xiàn)場的生產(chǎn)指揮與管理。
3.4.5負責(zé)每周或者分項工程施工前對施工班組下達施工任務(wù)單。
3.4.6負責(zé)施工過程中定位測量與組織督促施工班組做好自檢互檢。
3.4.7負責(zé)編制單位工程月進度計劃,并指導(dǎo)施工班組實施。
3.5質(zhì)檢員崗位職責(zé)
3.5.1負責(zé)對原材料、施工過程、工程交工過程的監(jiān)視與測量,監(jiān)視與測量
過程出現(xiàn)的不合格按公司有關(guān)規(guī)定執(zhí)行。并做好質(zhì)量檢查日記。
3.5.2負責(zé)對施工過程監(jiān)視與測量后的狀態(tài)標(biāo)識與管理。
3.5.3負責(zé)對工程維修結(jié)果的檢查驗收。
3.5.4負責(zé)對監(jiān)視(測)與測量裝置管理,建立項目部監(jiān)視(測)與測量裝
置臺帳。
3.5.5質(zhì)檢員助理協(xié)助質(zhì)檢員做好質(zhì)量檢查檢驗工作。
3.6安全員崗位職責(zé)
3.6.1協(xié)助項目經(jīng)理履行安全生產(chǎn)職責(zé),做好施工現(xiàn)場安全管理,督促班組
做好安全生產(chǎn)工作;
3.6.2負責(zé)組織貫徹落實安全生產(chǎn)責(zé)任制,執(zhí)行上級與公司各項安全生產(chǎn)規(guī)
章制度,組織項目職工進行安全教育與業(yè)務(wù)指導(dǎo),負責(zé)年度職工安全的考試,做
好評比工作。
3.6.3忠于職守,堅持原則,督促一線施工人員嚴格按照安全操作規(guī)程、安
全施工方案、安全技術(shù)交底要求辦事,對違反安全規(guī)定的行為予及時制止并給予
處罰,掌握施工現(xiàn)場安全生產(chǎn)動態(tài),做到防患予未然。
3.6.4督促安全施工方案實施,每日進行安全巡查,發(fā)現(xiàn)事故隱患及時糾正。
如遇緊急情況,立即制止生產(chǎn),及時向上級報告情況。
3.6.5參加工傷事故的調(diào)查取證、處理,做好項目部工傷事故統(tǒng)計、分析與
報告,將完整的事故材料報公司科室。
3.6.6負責(zé)將各竣工項目部安全資料裝訂好交公司歸檔。
3.6.7積極組織開展安全文明施工活動,制定安全生產(chǎn)文明施工目標(biāo)計劃,
并上報公司有關(guān)部門。
3.6.8負責(zé)檢查督促項目部特種作業(yè)人員堅持持證上崗;督促序列項目部工
長嚴格按安全施工組織設(shè)計施工。
3.6.9定期與不定期地對項目部機械設(shè)備進行安全技術(shù)檢查,建立嚴格的維
修保養(yǎng)制度,負責(zé)項目部的施工機械設(shè)備的使用、保護、保養(yǎng),確保機械在正常
情況下運轉(zhuǎn),大、中型機械設(shè)備完好率達公司規(guī)定目標(biāo)。
3.6.10協(xié)助設(shè)備部,認真做好特殊工種的技術(shù)培訓(xùn)工作。
3.7財務(wù)會計崗位職責(zé)
3.7.1認真執(zhí)行會計法律法規(guī)與財務(wù)制度,按照《會計基礎(chǔ)工作規(guī)范》及公
司有關(guān)的規(guī)定,搞好會計核算與會計管理工作。
3.7.2按照公司有關(guān)的規(guī)定建賬,做到會計核算辦法、會計核算程序、會計
核算口徑與上級財務(wù)部門一致。
3.7.3及時編制月度財務(wù)計劃,調(diào)節(jié)好生產(chǎn)用資金,保證生產(chǎn)正常進行。
3.7.4正確、及時做好施工生產(chǎn)成本核算,定期做好成本分析。
3.7.5正確、及時做好工程財務(wù)結(jié)算工作,真實反映工程收入、施工成本與
工程欠款等情況。
3.7.6做好財產(chǎn)物資的清理盤點與應(yīng)收款項的清理清收工作。
3.7.7把好本單位費用支出審核關(guān),評估內(nèi)部會計操縱與牽制情況。
3.7.8做好會計核算資料的整理與歸檔工作。
3.8計劃管理員崗位職責(zé)
3.8.1認真貫徹執(zhí)行上級有關(guān)技術(shù)政策、文件、定額與本單位的計劃管理制
度;
3.8.2及時編制施工進度與材料計劃,負責(zé)工程預(yù)決算、季度核算、結(jié)算的
編制。
3.8.3參加招投標(biāo)工作,并嚴格按投標(biāo)文件要求,正確編制好投標(biāo)預(yù)算。
3.8.4定時對各項計劃進行分析、總結(jié),對不符實際的計劃進行調(diào)整,使其
對工程施工直到指導(dǎo)性作用。
3.8.5及時編制有關(guān)報表,年末協(xié)助財務(wù)人員做好分配工作。
3.9資料員崗位職責(zé)
3.9.1負責(zé)本項目部文件、資料的收集、整理、發(fā)放與管理。
3.9.2負責(zé)項目技術(shù)文件及與業(yè)主等往來文件、受控文件的登記、管理。
3.9.3負責(zé)項目部所有質(zhì)量記錄的收集、整理。
3.9.4負責(zé)向顧客提供工程竣工資料。
3.9.5負責(zé)進場原材料的質(zhì)量檢測與復(fù)試。
3.9.6、建立項目部所有使用的檢驗、測量與試驗設(shè)備的臺帳與檔案。
3.10材料管理員崗位職責(zé)
3.10.1按照公司有關(guān)的規(guī)定做好本職及兼職工作。
3.10.2好本單位材料物資的計量驗收、領(lǐng)用發(fā)出與庫存管理工作。
3.10.3按照公司統(tǒng)一的會計核算辦法與操作程序,做好本單位實物資產(chǎn)的
收、發(fā)、存的核算工作。
3.10.4做好本單位施工生產(chǎn)耗用材料、物資的領(lǐng)用發(fā)放、匯總分配,按核
算期編制好耗用匯總分配表。
3.10.5按照公司有關(guān)的規(guī)定,做好會計核算。
3.10.6定期對所管轄實物資產(chǎn)、貨幣資金進行清理盤點,做到賬物相符、
賬款相符。
3.10.7協(xié)助單位總賬會計做好會計管理與會計核算工作。
3.11材料采購員崗位職責(zé)
3.11.1認真貫徹執(zhí)行國家法律法規(guī)與公司各項規(guī)章制度。
3.11.2刻苦學(xué)習(xí)與鉆研業(yè)務(wù)知識,努力提高業(yè)務(wù)水平與自身素養(yǎng),做到廉
政采購。
3.11.3負責(zé)做好項目部的材料采購工作。
3.11.4負責(zé)收集材料價格、貨源等信息,為進行供方評價與材料價格招標(biāo)
提供根據(jù)。
3.11.5協(xié)助施工員與質(zhì)檢員做好材料進貨檢驗工作,負責(zé)對不合格材料退
貨。
3.11.6按規(guī)定做好材料采購過程中的環(huán)境認證工作。
六、勞動力組織
1、各階段要緊工種勞動力配備計劃
1.1、由于前期涉及到場地平面布置、臨時工程的施工、設(shè)備進場,另外本工
程建筑面積較大,施工期短,特別是基礎(chǔ)及上部結(jié)構(gòu)需在短期內(nèi)完成,固所需施工
人數(shù)較多,需前期進場工作人員應(yīng)充足,并針對性地進行人力、物力、財力的調(diào)配。
我們公司具有多年有關(guān)經(jīng)驗,并有相當(dāng)實力的技術(shù)干部、技術(shù)工人與先進的施工機
械,我們確信能在較短的時間內(nèi)組織施工隊伍進場,保證準時開工。
1.2、根據(jù)工程的平面布置與結(jié)構(gòu)特點及施工承包范圍,組合項目體管理人員:項
目經(jīng)理1人,項目副經(jīng)理1人,項目工程師1人,施工員與質(zhì)量員、技術(shù)員、翻樣、
材料員等。
1.3、勞動力安排:施工階段施工人數(shù)如下表,中間結(jié)構(gòu)驗收后,進入內(nèi)粉及裝
飾階段,部分裝飾工穿插于主體結(jié)構(gòu)進行施工。
2各階段要緊工種勞動力配備計劃表
各工種高峰
工種基礎(chǔ)階段主體階段裝飾階段水電安裝時人數(shù)
木工4030
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準確性、安全性和完整性, 同時也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 殘疾人旅游咨詢兼職就業(yè)協(xié)議
- 購物中心運動品牌區(qū)域承包經(jīng)營合同
- 智能門鎖系統(tǒng)與云平臺對接安裝維護服務(wù)協(xié)議
- 海外施工安全圍欄租賃及配套配件供應(yīng)協(xié)議
- 物流運輸合作協(xié)議忠誠協(xié)議戰(zhàn)爭災(zāi)害不可抗力條款及供應(yīng)鏈
- 文化產(chǎn)業(yè)市場代理補充合同
- 專利許可擔(dān)保補充協(xié)議
- 游艇航海雷達租賃與操作培訓(xùn)協(xié)議
- 數(shù)據(jù)庫運營維護服務(wù)合作協(xié)議
- 抖音區(qū)域生活服務(wù)提供商合作框架協(xié)議
- 印染行業(yè)安全培訓(xùn)
- 公益慈善資金使用承諾書
- 2024年中考二輪專題復(fù)習(xí)道德與法治主觀題答題技巧(小論文)之演講稿
- 國有資產(chǎn)投資管理公司組建方案(3篇)
- 新版標(biāo)準化機電專業(yè)管理體系解讀課件
- 大學(xué)生心理健康教育(石家莊工程職業(yè)學(xué)院)知到智慧樹答案
- 第五課 在和睦家庭中成長 說課稿-2024-2025學(xué)年高中政治統(tǒng)編版選擇性必修二法律與生活
- 實+用法律基礎(chǔ)-形成性考核任務(wù)一-國開(ZJ)-參考資料
- 環(huán)保組織項目監(jiān)督管理制度
- 大米加工項目可行性研究報告
- GB/T 23473-2024林業(yè)植物及其產(chǎn)品調(diào)運檢疫規(guī)程
評論
0/150
提交評論